RERA: A51800043517

Ellora Heights

by Ellora Realcon LLP Partnership
Certificate Signed P51700006180
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700006180
Registration No.
REA51700011938
Registration Date
2017-08-14
Developer
Ellora Realcon LLP Partnership
Project Bank
ICICI BANK LIMITED
Proposed Possession
2019-07-31
Revised Possession
2019-07-31
Extended Possession
2021-01-30
Units Sold
0
Buildings
1
Project Area
1407.14 sq.m
Total FSI
3407.64
Approved FSI
3407.64
MahaRERA QR
Ellora Heights
MahaRERA — P51700006180
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors23
Sanctioned23
🅿️Closed Parking30
📅Completion2019-07-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1 Bhk 39.7599983215332 0 0 0
0%
2 Bhk 53.97999954223633 0 0 0
0%
2 Bhk 58.9900016784668 0 0 0
0%

Ellora Heights

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 39.76 80 44 36
55%
2 BHK 53.98 40 22 18
55%
2 BHK 58.99 17 9 8
53%

Construction Progress

Ellora Heights

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 95%
Energy management
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 95%
Solid Waste Management And Disposal 95%
Storm Water Drains 95%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water 95%
Water Conservation, Rain water Harvesting 100%
Water Supply 95%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.