RERA: A51800043517

Epitome

by Alvess Developers Private Limited Company
Certificate SignedP51800010680

Project Information

RERA Certificate No.
P51800010680
Registration No.
REA51800017192
Registration Date
2017-08-31
Developer
Alvess Developers Private Limited Company
Architect
Hafeez
Project Bank
UNION BANK OF INDIA
Proposed Possession
2019-12-31
Revised Possession
2019-12-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
1396.30 sq.m
Total FSI
2679.25
Approved FSI
2679.25
MahaRERA QR
Epitome
MahaRERA — P51800010680
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors69
Sanctioned69
🚗Open Parking51
🅿️Closed Parking51
📅Completion2019-12-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk89.7300033569336000
0%
3Bhk123.58999633789062000
0%
3Bhk130.94000244140625000
0%
3Bhk133.4600067138672000
0%
3Bhk145.14999389648438000
0%
4Bhk187.02000427246094000
0%
4Bhk220.7100067138672000
0%
5Bhk257.9700012207031000
0%
Shop19.959999084472656000
0%
Shop47.22999954223633000
0%
Shop74.52999877929688000
0%

Building 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK89.73101
0%
3 BHK123.59440
100%
3 BHK130.94303
0%
3 BHK133.46440
100%
3 BHK145.15404
0%
4 BHK187.02110
100%
4 BHK220.71101
0%
5 BHK257.97431
75%
Shop19.96110
100%
Shop47.23110
100%
Shop74.53110
100%

Construction Progress

Building 1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises70%
Overall Percentage of Completion of the work done For the entire Building /Wing75%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure70%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing70%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure70%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)5%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.