📞 +91 98200 30685 ✉️
RERA: A51800043517

EVERSHINE AMAVI 303 PHASE 3

by EVERSHINE DEVELOPERS Partnership
Certificate Signed P99000024753
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P99000024753
Registration No.
REA99000070207
Registration Date
2021-09-08
Developer
EVERSHINE DEVELOPERS Partnership
Project Bank
HDFC BANK
Proposed Possession
2024-12-30
Revised Possession
1900-01-01
Extended Possession
2025-12-30
Units Sold
0
Buildings
7
Project Area
12650.00 sq.m
Total FSI
24001.20
Approved FSI
24001.20
MahaRERA QR
EVERSHINE AMAVI 303 PHASE 3
MahaRERA — P99000024753
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors16
Sanctioned16
🚗Open Parking8
🅿️Closed Parking1
📅Completion2024-12-30
🏗️Proposed Floors16
Sanctioned16
🚗Open Parking8
🅿️Closed Parking1
📅Completion2024-12-30
🏗️Proposed Floors16
Sanctioned16
🚗Open Parking8
🅿️Closed Parking1
📅Completion2024-12-30
🏗️Proposed Floors16
Sanctioned16
🚗Open Parking8
🅿️Closed Parking1
📅Completion2024-12-30
🏗️Proposed Floors16
Sanctioned16
🚗Open Parking8
🅿️Closed Parking1
📅Completion2024-12-30
🏗️Proposed Floors16
Sanctioned16
🚗Open Parking11
🅿️Closed Parking1
📅Completion2024-12-30
🏗️Proposed Floors16
Sanctioned16
🚗Open Parking8
🅿️Closed Parking1
📅Completion2024-12-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 33.349998474121094 0 0 0
0%
1Bhk 33.5 0 0 0
0%
1Bhk 37.38999938964844 0 0 0
0%
2Bhk 44.09000015258789 0 0 0
0%
2Bhk 44.54999923706055 0 0 0
0%
2Bhk 45.869998931884766 0 0 0
0%
2Bhk 45.93000030517578 0 0 0
0%
2Bhk 46.4900016784668 0 0 0
0%
Shop 21.59000015258789 0 0 0
0%
Shop 22.1200008392334 0 0 0
0%
Shop 22.149999618530273 0 0 0
0%
Shop 22.190000534057617 0 0 0
0%
Shop 23.84000015258789 0 0 0
0%
Shop 24.079999923706055 0 0 0
0%
Shop 24.690000534057617 0 0 0
0%
Shop 34.84000015258789 0 0 0
0%
Shop 34.93000030517578 0 0 0
0%
Shop 35.54999923706055 0 0 0
0%
Shop 35.599998474121094 0 0 0
0%
Shop 36.630001068115234 0 0 0
0%

Building No 24

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 33.35 28 22 6
79%
1 BHK 33.5 28 11 17
39%
1 BHK 37.39 54 31 23
57%

Building No 25

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 33.35 28 1 27
4%
1 BHK 33.5 28 6 22
21%
1 BHK 37.39 54 12 42
22%

Building No 26

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 33.35 28 0 28
0%
1 BHK 33.5 28 0 28
0%
1 BHK 37.39 54 0 54
0%

Building No 6

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 44.55 28 0 28
0%
2 BHK 46.49 26 0 26
0%
Shop 22.15 2 2 0
100%
Shop 23.84 1 1 0
100%
Shop 34.84 1 1 0
100%

Building No 7

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 44.09 14 0 14
0%
2 BHK 45.87 28 0 28
0%
2 BHK 45.93 12 0 12
0%
Shop 22.12 4 3 1
75%
Shop 24.69 1 1 0
100%
Shop 35.55 2 2 0
100%
Shop 35.6 1 1 0
100%
Shop 36.63 1 1 0
100%

Building No 8

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 44.55 28 0 28
0%
2 BHK 46.49 26 0 26
0%
Shop 22.19 2 2 0
100%
Shop 24.08 1 1 0
100%
Shop 34.93 1 1 0
100%

Building No 9

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 44.55 28 0 28
0%
2 BHK 46.49 26 14 12
54%
Shop 21.59 1 1 0
100%
Shop 22.19 2 2 0
100%
Shop 24.08 1 1 0
100%
Shop 34.93 1 1 0
100%

Construction Progress

BUILDING NO 24

Basement (if any)100%

Building No 24

Excavation100%

BUILDING NO 24

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.15%

Building No 24

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate10%

BUILDING NO 24

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%

Building No 24

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises50%

BUILDING NO 24

Plinth100%
Podiums (if any) 100%

Building No 24

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 24

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure90%

Building No 24

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%

BUILDING NO 24

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%

Building No 24

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing15%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure90%

BUILDING NO 25

Basement (if any)100%

Building No 25

Excavation100%

BUILDING NO 25

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.15%

Building No 25

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate10%

BUILDING NO 25

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%

Building No 25

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises50%

BUILDING NO 25

Plinth100%
Podiums (if any) 100%

Building No 25

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 25

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure90%

Building No 25

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%

BUILDING NO 25

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%

Building No 25

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing15%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure90%

BUILDING NO 26

Basement (if any)100%

Building No 26

Excavation100%

BUILDING NO 26

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.15%

Building No 26

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate10%

BUILDING NO 26

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%

Building No 26

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises50%

BUILDING NO 26

Plinth100%
Podiums (if any) 100%

Building No 26

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 26

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure90%

Building No 26

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%

BUILDING NO 26

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%

Building No 26

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing15%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure90%

BUILDING NO 6

Basement (if any)100%

Building No 6

Excavation100%

BUILDING NO 6

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.15%

Building No 6

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate10%

BUILDING NO 6

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%

Building No 6

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises50%

BUILDING NO 6

Plinth100%
Podiums (if any) 100%

Building No 6

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 6

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure90%

Building No 6

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%

BUILDING NO 6

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%

Building No 6

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing15%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure90%

BUILDING NO 7

Basement (if any)100%

Building No 7

Excavation100%

BUILDING NO 7

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.15%

Building No 7

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate10%

BUILDING NO 7

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%

Building No 7

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises50%

BUILDING NO 7

Plinth100%
Podiums (if any) 100%

Building No 7

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 7

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure90%

Building No 7

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%

BUILDING NO 7

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%

Building No 7

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing15%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure90%

BUILDING NO 8

Basement (if any)100%

Building No 8

Excavation100%

BUILDING NO 8

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.15%

Building No 8

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate10%

BUILDING NO 8

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%

Building No 8

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises50%

BUILDING NO 8

Plinth100%
Podiums (if any) 100%

Building No 8

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 8

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure90%

Building No 8

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%

BUILDING NO 8

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%

Building No 8

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing15%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure90%

BUILDING NO 9

Basement (if any)100%

Building No 9

Excavation100%

BUILDING NO 9

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.15%

Building No 9

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate10%

BUILDING NO 9

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%

Building No 9

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises50%

BUILDING NO 9

Plinth100%
Podiums (if any) 100%

Building No 9

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 9

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure90%

Building No 9

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%

BUILDING NO 9

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%

Building No 9

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing15%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure90%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements 10%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 5%
Solid Waste Management And Disposal
Storm Water Drains 5%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water 10%
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.