RERA: A51800043517

Fuego

by Hilton Infrastructure
Certificate SignedP51900009939

Project Information

RERA Certificate No.
P51900009939
Registration No.
REA51900016408
Registration Date
2021-09-09
Developer
Hilton Infrastructure
Architect
Irani Architects
Project Bank
ICICI BANK LIMITED
Proposed Possession
2022-12-30
Revised Possession
2022-12-30
Extended Possession
2024-12-30
Total Units
220
Units Sold
122 (55%)
Buildings
3
Project Area
4245.86 sq.m
Total FSI
21251.83
Approved FSI
15936.18
MahaRERA QR
Fuego
MahaRERA — P51900009939
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors30
Sanctioned30
🏠Habitable22
🔢Total Units210
🏡Residential209
🏢Non-Residential1
⬇️Basements2
🅿️Closed Parking129
📅Completion2023-12-30
🏗️Proposed Floors17
Sanctioned17
🏠Habitable17
🔢Total Units10
🏡Residential10
⬇️Basements2
🅿️Closed Parking7
📅Completion2022-12-30
🏗️Proposed Floors12
Sanctioned12
⬇️Basements2
🅿️Closed Parking54
📅Completion2022-12-30

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1.5Bhk46.369998931884766000
0%
1Bhk31.09000015258789000
0%
1Bhk32.61000061035156000
0%
1Bhk35.86000061035156000
0%
1Bhk36.06999969482422000
0%
1Bhk38.5000
0%
1Bhk39.790000915527344000
0%
1Rk000
0%
2Bhk54.56999969482422000
0%
2Bhk54.93000030517578000
0%
2Bhk56.33000183105469000
0%
2Bhk58.119998931884766000
0%
2Bhk59.86000061035156000
0%
2Bhk66.5000
0%
2Bhk71.87999725341797000
0%
2Bhk75.47000122070312000
0%
2Bhk77.23999786376953000
0%

Building A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.091486
57%
1 BHK32.6114113
79%
1 BHK36.0713310
23%
1 BHK39.7914311
21%
1.5 BHK46.3714410
29%
2 BHK54.5714410
29%
2 BHK54.9316511
31%
2 BHK56.33716
14%
2 BHK58.12752
71%
2 BHK59.861459
36%
2 BHK66.530219
70%
2 BHK71.8826206
77%
2 BHK75.4721183
86%
2 BHK77.24660
100%

Building B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK35.86110
100%
1 BHK38.5963
67%

Building C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1RK000
0%

Construction Progress

BUILDING A

Basement (if any)100%

Building A

Excavation100%

BUILDING A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%

Building A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate70%

BUILDING A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%

Building A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises82%

BUILDING A

Plinth100%
Podiums (if any) 100%

Building A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises40%

BUILDING A

Sanitary Fittings within the flats / premises75%
Slabs of Super Structure100%

Building A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.75%

BUILDING A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks88%

Building A

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing65%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

BUILDING B

Basement (if any)100%

Building B

Excavation100%

BUILDING B

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building B

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

BUILDING B

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building B

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

BUILDING B

Plinth100%
Podiums (if any) 100%

Building B

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

BUILDING B

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building B

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING B

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building B

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

BUILDING C

Basement (if any)100%

Building C

Excavation100%

BUILDING C

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building C

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

BUILDING C

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building C

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

BUILDING C

Plinth100%
Podiums (if any) 100%

Building C

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

BUILDING C

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building C

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING C

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building C

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station75%
Energy management
Fire Protection And Fire Safety Requirements60%
FITNESS CENTER
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)75%
Solid Waste Management And Disposal35%
Storm Water Drains65%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water65%
Water Conservation, Rain water Harvesting100%
Water Supply65%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.