📞 +91 98200 30685 ✉️
RERA: A51800043517

Fuego

by Hilton Infrastructure
Certificate Signed P51900009939
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51900009939
Registration No.
REA51900016408
Registration Date
2021-09-09
Developer
Hilton Infrastructure
Architect
Irani Architects
Project Bank
ICICI BANK LIMITED
Proposed Possession
2022-12-30
Revised Possession
2022-12-30
Extended Possession
2024-12-30
Total Units
220
Units Sold
122 (55%)
Buildings
3
Project Area
4245.86 sq.m
Total FSI
21251.83
Approved FSI
15936.18
MahaRERA QR
Fuego
MahaRERA — P51900009939
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors30
Sanctioned30
🏠Habitable22
🔢Total Units210
🏡Residential209
🏢Non-Residential1
⬇️Basements2
🅿️Closed Parking129
📅Completion2023-12-30
🏗️Proposed Floors17
Sanctioned17
🏠Habitable17
🔢Total Units10
🏡Residential10
⬇️Basements2
🅿️Closed Parking7
📅Completion2022-12-30
🏗️Proposed Floors12
Sanctioned12
⬇️Basements2
🅿️Closed Parking54
📅Completion2022-12-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1.5Bhk 46.369998931884766 0 0 0
0%
1Bhk 31.09000015258789 0 0 0
0%
1Bhk 32.61000061035156 0 0 0
0%
1Bhk 35.86000061035156 0 0 0
0%
1Bhk 36.06999969482422 0 0 0
0%
1Bhk 38.5 0 0 0
0%
1Bhk 39.790000915527344 0 0 0
0%
1Rk 0 0 0
0%
2Bhk 54.56999969482422 0 0 0
0%
2Bhk 54.93000030517578 0 0 0
0%
2Bhk 56.33000183105469 0 0 0
0%
2Bhk 58.119998931884766 0 0 0
0%
2Bhk 59.86000061035156 0 0 0
0%
2Bhk 66.5 0 0 0
0%
2Bhk 71.87999725341797 0 0 0
0%
2Bhk 75.47000122070312 0 0 0
0%
2Bhk 77.23999786376953 0 0 0
0%

Building A

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 31.09 14 8 6
57%
1 BHK 32.61 14 11 3
79%
1 BHK 36.07 13 3 10
23%
1 BHK 39.79 14 3 11
21%
1.5 BHK 46.37 14 4 10
29%
2 BHK 54.57 14 4 10
29%
2 BHK 54.93 16 5 11
31%
2 BHK 56.33 7 1 6
14%
2 BHK 58.12 7 5 2
71%
2 BHK 59.86 14 5 9
36%
2 BHK 66.5 30 21 9
70%
2 BHK 71.88 26 20 6
77%
2 BHK 75.47 21 18 3
86%
2 BHK 77.24 6 6 0
100%

Building B

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 35.86 1 1 0
100%
1 BHK 38.5 9 6 3
67%

Building C

Type Carpet (sq.ft) Total Booked Available Status
1RK 0 0 0
0%

Construction Progress

BUILDING A

Basement (if any)100%

Building A

Excavation100%

BUILDING A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%

Building A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate70%

BUILDING A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%

Building A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises82%

BUILDING A

Plinth100%
Podiums (if any) 100%

Building A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises40%

BUILDING A

Sanitary Fittings within the flats / premises75%
Slabs of Super Structure100%

Building A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.75%

BUILDING A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks88%

Building A

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing65%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

BUILDING B

Basement (if any)100%

Building B

Excavation100%

BUILDING B

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building B

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

BUILDING B

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building B

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

BUILDING B

Plinth100%
Podiums (if any) 100%

Building B

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

BUILDING B

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building B

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING B

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building B

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

BUILDING C

Basement (if any)100%

Building C

Excavation100%

BUILDING C

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building C

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

BUILDING C

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building C

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

BUILDING C

Plinth100%
Podiums (if any) 100%

Building C

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

BUILDING C

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building C

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING C

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building C

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 75%
Energy management
Fire Protection And Fire Safety Requirements 60%
FITNESS CENTER
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 75%
Solid Waste Management And Disposal 35%
Storm Water Drains 65%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water 65%
Water Conservation, Rain water Harvesting 100%
Water Supply 65%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.