📞 +91 98200 30685 ✉️
RERA: A51800043517

Gami and Jaydeep Elanza

by M/S REAL INFRASTRUCTURE CO
Certificate Signed P51800047428
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800047428
Registration No.
REA51800121163
Registration Date
2023-11-22
Developer
M/S REAL INFRASTRUCTURE CO
Architect
Archo Consultants
Project Bank
AU SMALL FINANCE BANK LIMITED
Proposed Possession
2025-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
1669.00 sq.m
Total FSI
11032.20
Approved FSI
11031.43
MahaRERA QR
Gami and Jaydeep Elanza
MahaRERA — P51800047428
Scan to verify on MahaRERA portal

Wing-wise Details

📅Completion2025-12-31
📅Completion2025-12-31

Apartment Configurations

A Wing

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 52.03 18 18 0
100%
2 BHK 56.21 11 1 10
9%
2 BHK 57.6 6 1 5
17%
2 BHK 60.39 5 1 4
20%
2 BHK 62.71 5 0 5
0%
3 BHK 78.5 16 1 15
6%
3 BHK 84.08 16 0 16
0%
Shop 7.8 1 0 1
0%
Shop 13.1 1 0 1
0%
Shop 13.19 1 0 1
0%
Shop 14.86 1 0 1
0%
Shop 15.79 1 0 1
0%
Shop 16.07 1 0 1
0%
Shop 18.39 1 0 1
0%
Shop 18.49 1 0 1
0%

B Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 42.27 11 1 10
9%
1 BHK 44.59 5 0 5
0%
2 BHK 46.45 8 1 7
12%
2 BHK 49.24 6 2 4
33%
2 BHK 52.03 18 18 0
100%
2 BHK 57.14 6 1 5
17%
2 BHK 61.32 5 0 5
0%
2 BHK 63.17 15 7 8
47%
2 BHK 64.1 16 4 12
25%

Construction Progress

A wing

Basement (if any)100%

A Wing

Excavation100%

A wing

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%

A Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

A wing

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%

A Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises25%

A wing

Plinth100%
Podiums (if any) 0%

A Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

A wing

Sanitary Fittings within the flats / premises20%
Slabs of Super Structure94%

A Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.54%

A wing

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%

A Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure65%

B Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises25%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure94%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.54%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure65%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.