📞 +91 98200 30685 ✉️
RERA: A51800043517

Hari Tara Heights

by Ramdev Construction
Kept in Abeyance P51900014699
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51900014699
Registration No.
REA51900028278
Developer
Ramdev Construction
Project Bank
STATE BANK OF INDIA
Proposed Possession
2021-06-30
Revised Possession
1900-01-01
Extended Possession
2022-12-29
Buildings
1
Project Area
592.16 sq.m
Total FSI
2370.38
Approved FSI
593.90
MahaRERA QR
Hari Tara Heights
MahaRERA — P51900014699
Scan to verify on MahaRERA portal

Wing-wise Details

⬇️Basements1
🅿️Closed Parking24
📅Completion2020-12-31

Apartment Configurations

Hari Tara Heights

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 30.29 6 6 0
100%
1 BHK 30.94 1 1 0
100%
1 BHK 31.49 1 1 0
100%
1 BHK 33.72 1 1 0
100%
1 BHK 36.7 1 1 0
100%
1 BHK 43.76 4 3 1
75%
1 BHK 43.87 1 1 0
100%
1 BHK 46.64 1 1 0
100%
2 BHK 51.84 3 3 0
100%
2 BHK 57.97 2 2 0
100%
2 BHK 71.0 2 2 0
100%
2 BHK 75.07 1 1 0
100%
3 BHK 89.56 6 3 3
50%
3 BHK 89.7 4 3 1
75%
Office space 38.83 1 1 0
100%
Office space 56.3 1 1 0
100%
Office space 125.97 1 1 0
100%
Shop 6.97 1 1 0
100%
Shop 12.54 1 1 0
100%
Shop 40.69 1 1 0
100%
Shop 46.82 1 1 0
100%

Construction Progress

Hari Tara Heights

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate95%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing78%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises95%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 40%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.