Highland Park Building 2- K25 Wing A Phase 2
by Siddhi Gaurav Enterprises
Project Information
RERA Certificate No.
P51700005485
Registration No.
REA51700009504
Registration Date
2026-01-20
Developer
Siddhi Gaurav Enterprises
Architect
Joshi And Deshaware Associates
Project Bank
HDFC BANK
Proposed Possession
2024-12-30
Revised Possession
2024-12-30
Extended Possession
2025-12-29
Total Units
186
Units Sold
166 (89%)
Buildings
1
Project Area
2673.03 sq.m
Total FSI
10775.92
Approved FSI
3812.41
Highland Park Building 2- K25 Wing A Phase 2
MahaRERA — P51700005485
MahaRERA — P51700005485
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors36
✅Sanctioned36
🚗Open
Parking205
🅿️Closed Parking1
📅Completion2019-09-04
Apartment Configurations
Building 2- K25- Wing A
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 37.08 | 32 | 20 | 12 | 62% |
| 1 BHK | 38.34 | 32 | 27 | 5 | 84% |
| 2 BHK | 60.28 | 32 | 23 | 9 | 72% |
| 2 BHK | 61.52 | 32 | 26 | 6 | 81% |
| 2 BHK | 63.11 | 26 | 24 | 2 | 92% |
| 3 BHK | 78.22 | 32 | 30 | 2 | 94% |
Construction Progress
BUILDING 2- K25- WING A
Building 2- K25- Wing A
RERA Registered Amenities
✅Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical Meter Room, Sub-Station, Receiving Station
✅Energy management
✅Fire Protection And Fire Safety
Requirements
✅Landscaping & Tree Planting15%
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)1%
✅Solid Waste Management And Disposal
✅Storm Water Drains1%
✅Street Lighting5%
✅Treatment And Disposal Of Sewage And Sullage Water
✅Water Conservation, Rain water Harvesting
✅Water Supply