📞 +91 98200 30685✉️
RERA: A51800043517

Hill Ridge

by Sidhivinayak Realty Construction Private Limited Company
Certificate SignedP51800009010

Project Information

RERA Certificate No.
P51800009010
Registration No.
REA51800012522
Registration Date
2017-08-19
Developer
Sidhivinayak Realty Construction Private Limited Company
Architect
Gopal D Chiplunkar
Project Bank
YES BANK
Proposed Possession
2018-12-31
Revised Possession
2018-12-31
Extended Possession
2023-06-30
Units Sold
0
Buildings
1
Project Area
779.49 sq.m
Total FSI
2290.33
Approved FSI
1446.74
MahaRERA QR
Hill Ridge
MahaRERA — P51800009010
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
Sanctioned9
🅿️Closed Parking45
📅Completion2022-12-30

Apartment Configurations

Hill Ridge

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK45.97422
50%
2 BHK60.1610100
100%
2 BHK65.12101
0%
3 BHK77.85862
75%
3 BHK78.2871
88%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 Bhk45.970001220703125000
0%
2 Bhk60.15999984741211000
0%
2 Bhk65.12000274658203000
0%
3 Bhk77.8499984741211000
0%
3Bhk78.19999694824219000
0%

Construction Progress

HILL RIDGE

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Hill Ridge

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station100%
Energy management100%
Fire Protection And Fire Safety Requirements100%
Landscaping & Tree Planting100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal100%
Storm Water Drains100%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water100%
Water Conservation, Rain water Harvesting100%
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.