Project Information

RERA Certificate No.
P51800009010
Registration No.
REA51800012522
Registration Date
2017-08-19
Developer
SIDHIVINAYAK REALTY CONSTRUCTION PRIVATE LIMITED Company
Architect
Gopal D Chiplunkar
Project Bank
YES BANK
Proposed Possession
2018-12-31
Revised Possession
2018-12-31
Extended Possession
2023-06-30
Units Sold
0
Buildings
1
Project Area
779.49 sq.m
Total FSI
2290.33
Approved FSI
1446.74
MahaRERA QR
HILL RIDGE
MahaRERA — P51800009010
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
Sanctioned9
🅿️Closed Parking45
📅Completion2022-12-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1 Bhk 45.970001220703125 0 0 0
0%
2 Bhk 60.15999984741211 0 0 0
0%
2 Bhk 65.12000274658203 0 0 0
0%
3 Bhk 77.8499984741211 0 0 0
0%
3Bhk 78.19999694824219 0 0 0
0%

Hill Ridge

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 45.97 4 2 2
50%
2 BHK 60.16 10 10 0
100%
2 BHK 65.12 1 0 1
0%
3 BHK 77.85 8 6 2
75%
3 BHK 78.2 8 7 1
88%

Construction Progress

HILL RIDGE

Basement (if any)100%

Hill Ridge

Excavation100%

HILL RIDGE

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Hill Ridge

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

HILL RIDGE

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Hill Ridge

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

HILL RIDGE

Plinth100%
Podiums (if any) 0%

Hill Ridge

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

HILL RIDGE

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Hill Ridge

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

HILL RIDGE

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Hill Ridge

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management 100%
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 100%
Storm Water Drains 100%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 100%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.