KAATYAYNI ENCLAVE

by STARWING DEVELOPERS PRIVATE LIMITED Company
Certificate Signed P51800012277
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800012277
Registration No.
REA51800015384
Registration Date
2017-09-01
Developer
STARWING DEVELOPERS PRIVATE LIMITED Company
Architect
Dp Architects
Project Bank
DCB BANK LIMITED
Proposed Possession
2018-03-31
Revised Possession
2018-03-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
3178.60 sq.m
Total FSI
5880.41
Approved FSI
5880.41
MahaRERA QR
KAATYAYNI ENCLAVE
MahaRERA — P51800012277
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors2
Sanctioned2
📅Completion2018-03-31
🏗️Proposed Floors18
Sanctioned18
⬇️Basements1
🅿️Closed Parking12
📅Completion1900-01-01

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Rk 21.399999618530273 0 0 0
0%
1Rk 21.40999984741211 0 0 0
0%
1Rk 22.649999618530273 0 0 0
0%
1Rk 22.780000686645508 0 0 0
0%
1Rk 23.020000457763672 0 0 0
0%
1Rk 23.329999923706055 0 0 0
0%
1Rk 24.440000534057617 0 0 0
0%
1Rk 25.530000686645508 0 0 0
0%
2Bhk 83.1500015258789 0 0 0
0%
2Bhk 88.88999938964844 0 0 0
0%
2Bhk 88.9000015258789 0 0 0
0%
3Bhk 104.87999725341797 0 0 0
0%
4Bhk 230.1699981689453 0 0 0
0%

12Th Floor Wing A

Type Carpet (sq.ft) Total Booked Available Status
4 BHK 230.17 1 1 0
100%

B Wing

Type Carpet (sq.ft) Total Booked Available Status
1RK 21.4 4 2 2
50%
1RK 21.41 1 1 0
100%
1RK 22.65 1 1 0
100%
1RK 22.78 5 3 2
60%
1RK 23.02 4 2 2
50%
1RK 23.33 4 2 2
50%
1RK 24.44 4 2 2
50%
1RK 25.53 4 2 2
50%
2 BHK 83.15 5 2 3
40%
2 BHK 88.89 1 1 0
100%
2 BHK 88.9 5 3 2
60%
3 BHK 104.88 1 1 0
100%

Construction Progress

12TH FLOOR WING A

Basement (if any)100%

12Th Floor Wing A

Excavation100%

12TH FLOOR WING A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

12Th Floor Wing A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

12TH FLOOR WING A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

12Th Floor Wing A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

12TH FLOOR WING A

Plinth100%
Podiums (if any) 100%

12Th Floor Wing A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

12TH FLOOR WING A

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

12Th Floor Wing A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

12TH FLOOR WING A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

12Th Floor Wing A

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

B WING

Basement (if any)100%

B Wing

Excavation100%

B WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

B Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

B WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

B Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

B WING

Plinth100%
Podiums (if any) 100%

B Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

B WING

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

B Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

B WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

B Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 100%
Community Buildings 100%
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 100%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.