📞 +91 98200 30685✉️
RERA: A51800043517

Kakad Paradise Phase 2

by Kakad Housing Corporation Partnership
Certificate SignedP51700006750

Project Information

RERA Certificate No.
P51700006750
Registration No.
REA51700009516
Registration Date
2023-10-18
Developer
Kakad Housing Corporation Partnership
Architect
Ajay Mane
Project Bank
AXIS BANK
Proposed Possession
2024-06-30
Revised Possession
2024-06-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
7907.09 sq.m
Total FSI
11905.00
Approved FSI
11905.00
MahaRERA QR
Kakad Paradise Phase 2
MahaRERA — P51700006750
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors26
Sanctioned26
🅿️Closed Parking43
📅Completion2024-06-30
🏗️Proposed Floors25
Sanctioned25
🅿️Closed Parking43
📅Completion2024-06-30

Apartment Configurations

Wing C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK36.5316160
100%
1 BHK37.5984822
98%
1 BHK38.6638380
100%
1 BHK40.3211110
100%

Wing D

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK42.56220
100%
2 BHK50.051136-25
327%
2 BHK51.6319190
100%
2 BHK52.31330
100%
2 BHK53.8316160
100%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk36.529998779296875000
0%
1Bhk37.59000015258789000
0%
1Bhk38.65999984741211000
0%
1Bhk40.31999969482422000
0%
1Bhk42.560001373291016000
0%
2Bhk50.04999923706055000
0%
2Bhk51.630001068115234000
0%
2Bhk52.310001373291016000
0%
2Bhk53.83000183105469000
0%

Construction Progress

Wing C

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Wing D

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.