Project Information

RERA Certificate No.
P51800002863
Registration No.
REA51800009657
Registration Date
2017-08-04
Developer
Prathamesh Krupa Buildcon Private Limited Company
Architect
Haresh Mehta
Project Bank
THE SHAMRAO VITHAL COOPERATIVE BANK
Proposed Possession
2018-08-19
Revised Possession
2018-08-19
Extended Possession
2019-08-19
Units Sold
0
Buildings
1
Project Area
798.32 sq.m
Total FSI
2469.17
Approved FSI
2469.17
MahaRERA QR
Azad Nagar Kedar Darshan Chsl
MahaRERA — P51800002863
Scan to verify on MahaRERA portal

Wing-wise Details

šŸ—ļøProposed Floors15
āœ…Sanctioned15
šŸš—Open Parking17
šŸ…æļøClosed Parking1
šŸ“…Completion1900-01-01

Apartment Configurations

Kedar Darshan

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK57.16251411
56%
2 BHK57.6226179
65%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2Bhk57.15999984741211000
0%
2Bhk57.619998931884766000
0%

Construction Progress

KEDAR DARSHAN

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.97%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%

Kedar Darshan

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate97%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.98%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

āœ…Aggregate area of recreational Open Space98%
⬜Community Buildings
āœ…Electrical Meter Room, Sub-Station, Receiving Station98%
⬜Energy management
āœ…Fire Protection And Fire Safety Requirements98%
āœ…Landscaping & Tree Planting98%
āœ…Open Parking98%
āœ…Sewerage (Chamber, Lines, Septic Tank , STP)98%
⬜Solid Waste Management And Disposal
āœ…Storm Water Drains98%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
āœ…Water Conservation, Rain water Harvesting98%
āœ…Water Supply98%
CallWhatsApp
āœ‰ļø

Get in Touch

Our team will connect with you shortly

+91
šŸ”’ Your details are secure with us
⚔ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
šŸ‘‹ Looking for the right project? Let me help you find it!
šŸ—ļø
MPE Project Advisor
ā— Online now