📞 +91 98200 30685 ✉️
RERA: A51800043517

Lodha Amara - Tower 20, 21

by LODHA DEVELOPERS LIMITED Company
Certificate Signed P51700016961
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700016961
Registration No.
REA51700039000
Registration Date
2021-09-09
Developer
LODHA DEVELOPERS LIMITED Company
Project Bank
KOTAK MAHINDRA BANK LIMITED
Proposed Possession
2023-09-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
2588.00 sq.m
Total FSI
22294.61
Approved FSI
1787.10
MahaRERA QR
Lodha Amara - Tower 20, 21
MahaRERA — P51700016961
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors30
Sanctioned30
🅿️Closed Parking173
📅Completion2023-09-30
🏗️Proposed Floors30
Sanctioned30
🅿️Closed Parking173
📅Completion2023-09-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
2 Bhk Optima 48.869998931884766 0 0 0
0%
2 Bhk Optima 50.720001220703125 0 0 0
0%
2 Bhk S 42.84000015258789 0 0 0
0%
2 Bhk Ultima 57.650001525878906 0 0 0
0%
2 Bhk Ultima 57.84000015258789 0 0 0
0%
2 Bhk Ultima 62.43000030517578 0 0 0
0%
3Bhk 40.970001220703125 0 0 0
0%
3Bhk 48.869998931884766 0 0 0
0%
3Bhk 50.720001220703125 0 0 0
0%
3Bhk 57.599998474121094 0 0 0
0%
3Bhk 57.790000915527344 0 0 0
0%
3Bhk 62.43000030517578 0 0 0
0%

Tower 20

Type Carpet (sq.ft) Total Booked Available Status
2 BHK OPTIMA 48.87 24 24 0
100%
2 BHK OPTIMA 50.72 24 24 0
100%
2 BHK S 42.84 5 5 0
100%
2 BHK ULTIMA 57.65 58 58 0
100%
2 BHK ULTIMA 57.84 58 58 0
100%
2 BHK ULTIMA 62.43 4 3 1
75%

Tower 21

Type Carpet (sq.ft) Total Booked Available Status
3 BHK 40.97 5 5 0
100%
3 BHK 48.87 24 24 0
100%
3 BHK 50.72 24 24 0
100%
3 BHK 57.6 58 58 0
100%
3 BHK 57.79 58 58 0
100%
3 BHK 62.43 2 2 0
100%

Construction Progress

Tower 20

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing80%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Tower 21

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing80%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 100%
Closed Parkings 100%
Community Buildings 100%
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management 100%
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking 100%
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 100%
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 100%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.