Project Information

RERA Certificate No.
P51800000195
Registration No.
REA51800003445
Registration Date
2018-10-12
Developer
Macrotech Developers Limited Company
Architect
Vilas Desai & Associates
Project Bank
IDBI BANK
Proposed Possession
2018-01-31
Revised Possession
2018-01-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
1333.69 sq.m
Total FSI
26371.00
Approved FSI
26371.00
MahaRERA QR
Lodha Fiorenza
MahaRERA — P51800000195
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors37
Sanctioned37
⬇️Basements3
🅿️Closed Parking171
📅Completion2018-01-31
🏗️Proposed Floors45
Sanctioned45
⬇️Basements3
🅿️Closed Parking268
📅Completion2018-01-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
2Bhkt1 69.20999908447266 0 0 0
0%
2Bhkt2 74.41000366210938 0 0 0
0%
2Bhkt3 74.56999969482422 0 0 0
0%
3Bhklt1 112.38999938964844 0 0 0
0%
3Bhklt2 119.86000061035156 0 0 0
0%
3Bhklt3 120.11000061035156 0 0 0
0%
3Bhkt1 87.1500015258789 0 0 0
0%
3Bhkt1 136.3800048828125 0 0 0
0%
3Bhkt2 95.2699966430664 0 0 0
0%
3Bhkt2 150.67999267578125 0 0 0
0%
3Bhkt3 95.30999755859375 0 0 0
0%
3Bhkt3 150.89999389648438 0 0 0
0%
4 Bhk Type 1 109.41000366210938 0 0 0
0%
4 Bhk Type 2 114.66000366210938 0 0 0
0%
4Bhkt1 166.41000366210938 0 0 0
0%
4Bhkt2 170.57000732421875 0 0 0
0%
5Bhkt1 248.1300048828125 0 0 0
0%
5Bhkt2 269.9599914550781 0 0 0
0%
5Bhkt3 271.2799987792969 0 0 0
0%
5Bhkt4 289.45001220703125 0 0 0
0%

Milano

Type Carpet (sq.ft) Total Booked Available Status
3 BHKT1 136.38 1 1 0
100%
3 BHKT2 150.68 1 1 0
100%
3 BHKT3 150.9 1 1 0
100%
4 BHKT1 166.41 23 23 0
100%
4 BHKT2 170.57 20 20 0
100%
5 BHKT1 248.13 3 3 0
100%
5 BHKT2 269.96 2 2 0
100%
5 BHKT3 271.28 2 2 0
100%
5 BHKT4 289.45 2 2 0
100%

Roma

Type Carpet (sq.ft) Total Booked Available Status
2 BHKT1 69.21 6 6 0
100%
2 BHKT2 74.41 3 3 0
100%
2 BHKT3 74.57 31 31 0
100%
3 BHKLT1 112.39 6 6 0
100%
3 BHKLT2 119.86 3 3 0
100%
3 BHKLT3 120.11 31 31 0
100%
3 BHKT1 87.15 46 46 0
100%
3 BHKT2 95.27 7 7 0
100%
3 BHKT3 95.31 16 16 0
100%
4 BHK TYPE 1 109.41 2 2 0
100%
4 BHK TYPE 2 114.66 3 3 0
100%

Construction Progress

MILANO

Basement (if any)100%

Milano

Excavation100%

MILANO

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Milano

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

MILANO

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Milano

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

MILANO

Plinth100%
Podiums (if any) 100%

Milano

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

MILANO

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Milano

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

MILANO

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Milano

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

ROMA

Basement (if any)100%

Roma

Excavation100%

ROMA

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Roma

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

ROMA

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Roma

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

ROMA

Plinth100%
Podiums (if any) 100%

Roma

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

ROMA

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Roma

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

ROMA

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Roma

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Club Milano 100%
Community Buildings 100%
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 100%
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 100%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.