RERA: A51800043517

M M VALEY A2

by ALFA ENTERPRISES Partnership
Certificate Signed P51700010237
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700010237
Registration No.
REA51700019813
Registration Date
2021-09-09
Developer
ALFA ENTERPRISES Partnership
Architect
Joshi Deshaware & Associates
Project Bank
HDFC BANK
Proposed Possession
2022-12-30
Revised Possession
2022-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
3864.90 sq.m
Total FSI
4284.64
Approved FSI
2044.58
MahaRERA QR
M M VALEY A2
MahaRERA — P51700010237
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors24
Sanctioned24
🅿️Closed Parking1
📅Completion2022-12-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 34.689998626708984 0 0 0
0%
1Bhk 34.90999984741211 0 0 0
0%
1Bhk 35.70000076293945 0 0 0
0%
1Bhk 35.720001220703125 0 0 0
0%
1Bhk 36.61000061035156 0 0 0
0%
1Bhk 36.63999938964844 0 0 0
0%
2Bhk 45.02000045776367 0 0 0
0%
2Bhk 45.34000015258789 0 0 0
0%
2Bhk 47.40999984741211 0 0 0
0%
Shop 5.309999942779541 0 0 0
0%
Shop 10.970000267028809 0 0 0
0%
Shop 11.149999618530273 0 0 0
0%
Shop 13.100000381469727 0 0 0
0%
Shop 13.680000305175781 0 0 0
0%
Shop 14.59000015258789 0 0 0
0%
Shop 16.530000686645508 0 0 0
0%
Shop 17.09000015258789 0 0 0
0%
Shop 17.639999389648438 0 0 0
0%
Shop 18.559999465942383 0 0 0
0%
Shop 18.899999618530273 0 0 0
0%
Shop 18.969999313354492 0 0 0
0%
Shop 25.280000686645508 0 0 0
0%

A-2 Mm Valley Premium

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 34.69 23 22 1
96%
1 BHK 34.91 19 19 0
100%
1 BHK 35.7 18 16 2
89%
1 BHK 35.72 18 16 2
89%
1 BHK 36.61 5 3 2
60%
1 BHK 36.64 5 3 2
60%
2 BHK 45.02 18 17 1
94%
2 BHK 45.34 2 2 0
100%
2 BHK 47.41 3 3 0
100%
Shop 5.31 1 0 1
0%
Shop 10.97 2 0 2
0%
Shop 11.15 1 0 1
0%
Shop 13.1 1 0 1
0%
Shop 13.68 1 0 1
0%
Shop 14.59 1 0 1
0%
Shop 16.53 1 0 1
0%
Shop 17.09 1 0 1
0%
Shop 17.64 1 0 1
0%
Shop 18.56 1 0 1
0%
Shop 18.9 1 0 1
0%
Shop 18.97 1 0 1
0%
Shop 25.28 1 1 0
100%

Construction Progress

A-2 MM VALLEY PREMIUM

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.96%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.92%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks96%
Stilt Floor 100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 55%
Energy management
Fire Protection And Fire Safety Requirements 60%
Landscaping & Tree Planting 60%
Open Parking
Podium 90%
Sewerage (Chamber, Lines, Septic Tank , STP) 33%
Solar Panels
Solid Waste Management And Disposal
Storm Water Drains 60%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.