📞 +91 98200 30685 ✉️
RERA: A51800043517

MANTHAN EMBASSY

by MANTHAN DEVELOPMENT CORPORATION Partnership
Certificate Signed P51800004366
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800004366
Registration No.
REA51800011440
Registration Date
2023-07-17
Developer
MANTHAN DEVELOPMENT CORPORATION Partnership
Architect
Ram Aglave And Associates
Project Bank
JANATA SAHAKARI BANK LIMITED
Proposed Possession
2024-12-30
Revised Possession
2024-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
1611.10 sq.m
Total FSI
4029.41
Approved FSI
3542.18
MahaRERA QR
MANTHAN EMBASSY
MahaRERA — P51800004366
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors20
Sanctioned20
🅿️Closed Parking43
📅Completion2023-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
2Bhk 72.19000244140625 0 0 0
0%
4Bhk 111.25 0 0 0
0%
Office Space 38.709999084472656 0 0 0
0%
Shop 232.8000030517578 0 0 0
0%
Shop 271.739990234375 0 0 0
0%

Wing A

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 72.19 12 11 1
92%
4 BHK 111.25 1 1 0
100%
Office space 38.71 1 0 1
0%
Shop 69.03 1 1 0
100%
Shop 163.62 1 1 0
100%
Shop 271.74 1 1 0
100%

Construction Progress

Wing A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises20%
Overall Percentage of Completion of the work done For the entire Building /Wing36%
Plinth100%
Podiums (if any) 80%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises20%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure50%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing20%
X number of Basement(s) and Plinth0%
X number of Podiums80%
X number of Slabs of Super Structure50%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 50%
Energy management
Fire Protection And Fire Safety Requirements 25%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 25%
Solid Waste Management And Disposal 25%
Storm Water Drains 50%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply 25%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.