RERA: A51800043517

MAULI DESIRE

by MAULI SAI DEVELOPERS PVT LTD Company
Certificate Signed P51800001946
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800001946
Registration No.
REA51800005886
Registration Date
2024-06-03
Developer
MAULI SAI DEVELOPERS PVT LTD Company
Architect
Rasik Hingoo
Project Bank
HDFC BANK
Proposed Possession
2019-01-31
Revised Possession
2019-01-31
Extended Possession
2024-06-29
Units Sold
0
Buildings
2
Project Area
1427.70 sq.m
Total FSI
4735.00
Approved FSI
4735.00
MahaRERA QR
MAULI DESIRE
MahaRERA — P51800001946
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors15
Sanctioned15
🅿️Closed Parking12
📅Completion2023-06-30
🏗️Proposed Floors17
Sanctioned17
🅿️Closed Parking10
📅Completion2023-06-30

Apartment Configurations

Desire I

Type Carpet (sq.ft) Total Booked Available Status
REHAB 1 BHK 20.9 4 0 4
0%
REHAB 1 BHK 20.93 1 0 1
0%
REHAB 1 BHK 24.16 5 0 5
0%
REHAB 1 BHK 32.97 2 0 2
0%
REHAB 1 BHK 33.14 3 0 3
0%
REHAB SHOP 6.05 1 0 1
0%
REHAB SHOP 12.36 1 0 1
0%
REHAB SHOP 21.98 1 0 1
0%
REHAB SHOP 25.71 1 0 1
0%
SALE 1 BHK 20.9 3 3 0
100%
SALE 1 BHK 20.93 5 5 0
100%
SALE 1 BHK 24.16 1 1 0
100%
SALE 1 BHK 32.97 12 12 0
100%
SALE 1 BHK 33.14 10 10 0
100%
SALE SHOP 24.34 1 1 0
100%

Desire Ii

Type Carpet (sq.ft) Total Booked Available Status
REHAB 1 BHK 25.18 29 0 29
0%
REHAB 1 BHK 34.2 6 0 6
0%
REHAB SHOP 5.27 1 0 1
0%
REHAB SHOP 5.47 1 0 1
0%
REHAB SHOP 5.9 1 0 1
0%
REHAB SHOP 8.58 1 0 1
0%
REHAB SHOP 8.89 1 0 1
0%
REHAB SHOP 9.86 1 0 1
0%
REHAB SHOP 14.53 1 0 1
0%
REHAB SHOP 15.3 1 0 1
0%
SALE 1 BHK 25.18 6 6 0
100%
SALE 1 BHK 34.2 24 22 2
92%
SALE SHOP 12.92 1 1 0
100%
SALE SHOP 14.54 1 1 0
100%
SALE SHOP 16.0 1 1 0
100%
SALE SHOP 19.58 1 0 1
0%

Construction Progress

DESIRE I

Basement (if any)100%

Desire I

Excavation100%

DESIRE I

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%

Desire I

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate95%

DESIRE I

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%

Desire I

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises95%

DESIRE I

Plinth100%
Podiums (if any) 0%

Desire I

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises95%

DESIRE I

Sanitary Fittings within the flats / premises95%
Slabs of Super Structure100%

Desire I

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.95%

DESIRE I

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%

Desire I

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing95%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

DESIRE II

Basement (if any)100%

Desire Ii

Excavation100%

DESIRE II

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%

Desire Ii

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate95%

DESIRE II

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%

Desire Ii

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises95%

DESIRE II

Plinth100%
Podiums (if any) 0%

Desire Ii

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises95%

DESIRE II

Sanitary Fittings within the flats / premises95%
Slabs of Super Structure100%

Desire Ii

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.95%

DESIRE II

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%

Desire Ii

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing95%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 95%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 95%
Energy management
Fire Protection And Fire Safety Requirements 95%
Landscaping & Tree Planting 95%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 95%
Solid Waste Management And Disposal 95%
Storm Water Drains 95%
Street Lighting 95%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 95%
Water Supply 60%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.