Project Information

RERA Certificate No.
P51800000370
Registration No.
REA51800003562
Registration Date
2020-06-11
Developer
Skylink Hospitality Llp
Architect
M/S Dot Architects Pvt Ltd As L.S. / Architect
Project Bank
BANK OF BARODA
Proposed Possession
2021-06-30
Revised Possession
2021-06-30
Extended Possession
2023-12-30
Units Sold
0
Buildings
1
Project Area
1873.60 sq.m
Total FSI
7567.39
Approved FSI
5496.11
MahaRERA QR
Mirabilis
MahaRERA — P51800000370
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors15
Sanctioned15
⬇️Basements1
🅿️Closed Parking140
📅Completion2021-06-30

Apartment Configurations

Mirabilis

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK42.4915510
33%
1 BHK48.141376
54%
1 BHK49.8115510
33%
2 BHK63.751596
60%
2 BHK69.5213103
77%
2 BHK70.911569
40%
2 BHK76.211587
53%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk42.4900016784668000
0%
1Bhk48.13999938964844000
0%
1Bhk49.810001373291016000
0%
2Bhk63.75000
0%
2Bhk69.5199966430664000
0%
2Bhk70.91000366210938000
0%
2Bhk76.20999908447266000
0%

Construction Progress

MIRABILIS

Basement (if any)70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth70%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Mirabilis

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing17%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth70%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Business Center
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Entrance Lobby& Lift lobby
Fire Protection And Fire Safety Requirements
Gymasium
Indoor Games
Kids Play area, Activity area
Landscaping & Tree Planting
Open Parking
Pool changing rooms with shower area
Sewerage (Chamber, Lines, Septic Tank , STP)
Society room
Solid Waste Management And Disposal
Steam Room & changing room
Storm Water Drains
Street Lighting
Swimming Pool and Jacuzzi
Treatment And Disposal Of Sewage And Sullage Water
Virtual Games
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.