RERA: A51800043517

ORCA HEIGHTS

by A.P. ENTERPRISE Partnership
Certificate Signed P51800053104
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800053104
Registration No.
REA51800146788
Registration Date
2023-10-16
Developer
A.P. ENTERPRISE Partnership
Architect
Shri Shrikant Vichare
Project Bank
HDFC BANK
Proposed Possession
2029-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
1518.77 sq.m
Total FSI
4241.62
Approved FSI
1529.56
MahaRERA QR
ORCA HEIGHTS
MahaRERA — P51800053104
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors17
Sanctioned17
🅿️Closed Parking24
📅Completion2029-12-31
🏗️Proposed Floors2
Sanctioned2
📅Completion2029-12-31

Apartment Configurations

Wing A

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 37.08 14 0 14
0%
1 BHK 37.28 15 0 15
0%
1 BHK 43.36 1 0 1
0%
2 BHK 55.44 14 2 12
14%
Office space 14.24 1 0 1
0%
Office space 21.1 1 0 1
0%
Office space 23.16 1 0 1
0%
Office space 37.08 1 0 1
0%
Office space 37.28 1 0 1
0%
Office space 55.44 1 0 1
0%

Wing B

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 56.29 1 0 1
0%

Construction Progress

WING A

Basement (if any)100%

Wing A

Excavation100%

WING A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Wing A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

WING A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Wing A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing23%

WING A

Plinth100%
Podiums (if any) 0%

Wing A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING A

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure41%

Wing A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

WING A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Wing A

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums30%
X number of Slabs of Super Structure0%

WING B

Basement (if any)0%

Wing B

Excavation0%

WING B

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Wing B

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

WING B

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Wing B

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

WING B

Plinth0%
Podiums (if any) 0%

Wing B

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING B

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Wing B

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

WING B

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Wing B

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
COMPOUND WALL AND PAVEMENT AREA
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.