RERA: A51800043517

Orion -3

by Vijay Suraksha Realty Llp Partnership
Certificate SignedP51700006838

Project Information

RERA Certificate No.
P51700006838
Registration No.
REA51700012636
Registration Date
2020-06-10
Developer
Vijay Suraksha Realty Llp Partnership
Architect
M/S. Scapes Architects
Project Bank
ICICI BANK LIMITED
Proposed Possession
2020-12-30
Revised Possession
2020-12-30
Extended Possession
2021-10-30
Units Sold
0
Buildings
1
Project Area
546.00 sq.m
Total FSI
9658.45
Approved FSI
9658.45
MahaRERA QR
Orion -3
MahaRERA — P51700006838
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors28
Sanctioned28
🅿️Closed Parking161
📅Completion2020-06-30

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 Bhk82.95999908447266000
0%
2 Bhk90.54000091552734000
0%
3Bhk112.79000091552734000
0%
4Bhk174.6300048828125000
0%

Orion-3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK82.96808
0%
2 BHK90.54808
0%
3 BHK112.7942834
19%
4 BHK174.6315510
33%

Construction Progress

Orion-3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Common Amenities like Gym Common room containing mirror wooden flooring for yoga or meditation Room65%
Community Buildings100%
Electrical Meter Room, Sub-Station, Receiving Station75%
Energy management50%
Fire Protection And Fire Safety Requirements100%
Games room with carrom chess and cards65%
Guest rooms and Recreational Hall65%
Landscaping & Tree Planting90%
Open Parking
Reading room and Senior Citizen area small area and childproof room with soft rubber flooring65%
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Society Office50%
Solid Waste Management And Disposal100%
Storm Water Drains100%
Street Lighting90%
Treatment And Disposal Of Sewage And Sullage Water100%
Water Conservation, Rain water Harvesting100%
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.