Project Information

RERA Certificate No.
P51800033078
Registration No.
REA51800101889
Registration Date
2022-02-03
Developer
Sai Ganesh Properties and Holdings LLP Partnership
Architect
Pravin Kanekar
Project Bank
ICICI BANK LIMITED
Proposed Possession
2024-03-31
Revised Possession
1900-01-01
Extended Possession
2024-07-31
Units Sold
0
Buildings
1
Project Area
706.60 sq.m
Total FSI
2098.38
Approved FSI
2098.38
MahaRERA QR
PARLASHRAY CHSL
MahaRERA — P51800033078
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
Sanctioned9
🚗Open Parking1
🅿️Closed Parking28
📅Completion2024-03-31

Apartment Configurations

Parlashray Chsl

Type Carpet (sq.ft) Total Booked Available Status
1RK 38.55 1 1 0
100%
2 BHK 46.45 1 1 0
100%
2 BHK 60.39 6 1 5
17%
2 BHK 63.64 3 1 2
33%
2 BHK 67.82 1 1 0
100%
3 BHK 91.51 1 0 1
0%
3 BHK 92.53 1 1 0
100%
3 BHK 95.22 2 1 1
50%
MEMBER 63.17 1 1 0
100%
MEMBERS 63.64 2 2 0
100%
MEMBERS 67.54 6 6 0
100%
MEMBERS 96.62 3 3 0
100%

Construction Progress

PARLASHRAY CHSL

Basement (if any)100%

Parlashray Chsl

Excavation100%

PARLASHRAY CHSL

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Parlashray Chsl

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

PARLASHRAY CHSL

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Parlashray Chsl

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

PARLASHRAY CHSL

Plinth100%
Podiums (if any) 0%

Parlashray Chsl

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

PARLASHRAY CHSL

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Parlashray Chsl

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

PARLASHRAY CHSL

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Parlashray Chsl

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 70%
Energy management
Fire Protection And Fire Safety Requirements 30%
Landscaping & Tree Planting 20%
Open Parking 10%
Sewerage (Chamber, Lines, Septic Tank , STP) 30%
Solid Waste Management And Disposal 60%
Storm Water Drains 20%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 10%
Water Supply 60%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.