Project Information

RERA Certificate No.
P51800023003
Registration No.
REA51800061605
Registration Date
2021-09-08
Developer
JPV Realtors Private Limited Company
Project Bank
SARASWAT COOPERATIVE BANK LIMITED
Proposed Possession
2023-12-30
Revised Possession
1900-01-01
Extended Possession
2025-12-31
Total Units
31
Units Sold
31 (100%)
Buildings
1
Project Area
980.60 sq.m
Total FSI
2912.38
Approved FSI
2182.18
MahaRERA QR
Pratap Oasis
MahaRERA — P51800023003
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors17
Sanctioned17
🏠Habitable17
🔢Total Units31
🏡Residential31
🅿️Closed Parking37
📅Completion2023-12-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 38.18000030517578 0 0 0
0%
1Bhk 38.369998931884766 0 0 0
0%
1Bhk 38.459999084472656 0 0 0
0%
1Bhk 40.689998626708984 0 0 0
0%
2Bhk 52.400001525878906 0 0 0
0%
2Bhk 52.58000183105469 0 0 0
0%
2Bhk 56.47999954223633 0 0 0
0%
2Bhk 57.040000915527344 0 0 0
0%
4Bhk 106.55999755859375 0 0 0
0%

Pratap Oasis

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 38.18 1 1 0
100%
1 BHK 38.37 12 12 0
100%
1 BHK 38.46 11 11 0
100%
1 BHK 40.69 1 1 0
100%
2 BHK 52.4 1 1 0
100%
2 BHK 52.58 1 1 0
100%
2 BHK 56.48 1 1 0
100%
2 BHK 57.04 2 2 0
100%
4 BHK 106.56 1 1 0
100%

Construction Progress

Pratap Oasis

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises80%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises5%
Sanitary Fittings within the flats / premises5%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements 50%
Fitness Centre
Landscaping & Tree Planting
Open Parking 100%
Sewerage (Chamber, Lines, Septic Tank , STP) 60%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 50%
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.