Project Information

RERA Certificate No.
P51800001724
Registration No.
REA51800006064
Registration Date
2020-06-11
Developer
Ceear Land Developers LLP Partnership
Architect
Tushar Bhor
Project Bank
HDFC BANK
Proposed Possession
2021-06-30
Revised Possession
2021-06-30
Extended Possession
2024-03-31
Units Sold
0
Buildings
1
Project Area
2619.80 sq.m
Total FSI
7381.31
Approved FSI
7381.31
MahaRERA QR
Primo
MahaRERA — P51800001724
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors24
Sanctioned24
⬇️Basements2
🅿️Closed Parking126
📅Completion2020-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 41.470001220703125 0 0 0
0%
2Bhk 58.65999984741211 0 0 0
0%
3Bhk 89.63999938964844 0 0 0
0%
3Bhk 106.6500015258789 0 0 0
0%
3Bhk 135.89999389648438 0 0 0
0%

Primo

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 41.47 55 41 14
75%
2 BHK 58.66 59 47 12
80%
3 BHK 89.64 2 0 2
0%
3 BHK 106.65 6 0 6
0%
3 BHK 135.9 1 1 0
100%

Construction Progress

Primo

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate17%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.17%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises73%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises73%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises27%
Sanitary Fittings within the flats / premises27%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing35%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting 8%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains 50%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.