Rajkamal Park

by Prarthana Griha Nirman Partnership
Certificate SignedP51900010115
šŸ’¬ WhatsAppšŸ“ž Call

Project Information

RERA Certificate No.
P51900010115
Registration No.
REA51900018435
Registration Date
2021-09-09
Developer
Prarthana Griha Nirman Partnership
Architect
Chandrashekhar
Project Bank
AXIS BANK
Proposed Possession
2023-12-30
Revised Possession
2023-12-30
Extended Possession
2024-12-29
Total Units
162
Units Sold
103 (64%)
Buildings
2
Project Area
3150.83 sq.m
Total FSI
11650.47
Approved FSI
10953.91
MahaRERA QR
Rajkamal Park
MahaRERA — P51900010115
Scan to verify on MahaRERA portal

Wing-wise Details

šŸ—ļøProposed Floors8
āœ…Sanctioned8
šŸ Habitable8
šŸ”¢Total Units36
šŸ”Residential36
šŸ…æļøClosed Parking1
šŸ“…Completion2022-12-31
šŸ—ļøProposed Floors8
āœ…Sanctioned8
šŸ Habitable8
šŸ”¢Total Units126
šŸ”Residential126
šŸ…æļøClosed Parking1
šŸ“…Completion2022-12-31

Apartment Configurations

Composite Building No - 1 Wing B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK43.7928253
89%

Rajkamal Park Wing - A , B, C, D

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK35.76707
0%
1 BHK36.51752
71%
1 BHK36.53707
0%
1 BHK36.61743
57%
1 BHK36.77770
100%
1 BHK36.8928262
93%
1 BHK36.9721183
86%
1 BHK37.05770
100%
1 BHK40.78743
57%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk35.7599983215332000
0%
1Bhk36.5099983215332000
0%
1Bhk36.529998779296875000
0%
1Bhk36.61000061035156000
0%
1Bhk36.77000045776367000
0%
1Bhk36.88999938964844000
0%
1Bhk36.970001220703125000
0%
1Bhk37.04999923706055000
0%
1Bhk40.779998779296875000
0%
1Bhk43.790000915527344000
0%

Construction Progress

Composite Building No - 1 Wing B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Rajkamal Park Wing - A , B, C, D

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.94%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.92%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises97%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises95%
Sanitary Fittings within the flats / premises96%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks97%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.96%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing93%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
āœ…Electrical Meter Room, Sub-Station, Receiving Station100%
⬜Energy management
⬜Fire Protection And Fire Safety Requirements
āœ…Landscaping & Tree Planting100%
⬜Open Parking
āœ…Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
āœ…Storm Water Drains100%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
āœ…Water Conservation, Rain water Harvesting100%
āœ…Water Supply100%
CallWhatsApp
āœ‰ļø

Get in Touch

Our team will connect with you shortly

+91
šŸ”’ Your details are secure with us
⚔ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
šŸ‘‹ Looking for the right project? Let me help you find it!
šŸ—ļø
MPE Project Advisor
ā— Online now