📞 +91 98200 30685✉️
RERA: A51800043517

Regal Square Ph 4 Tower 6 And 8

by Dev Drashti Realty Private Limited
Certificate SignedP51700033625

Project Information

RERA Certificate No.
P51700033625
Registration No.
REA51700103121
Registration Date
2024-01-16
Developer
Dev Drashti Realty Private Limited
Project Bank
STATE BANK OF INDIA
Proposed Possession
2026-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
269
Units Sold
2 (1%)
Buildings
2
Project Area
1101.67 sq.m
Total FSI
10590.00
Approved FSI
10590.00
MahaRERA QR
Regal Square Ph 4 Tower 6 And 8
MahaRERA — P51700033625
Scan to verify on MahaRERA portal

Wing-wise Details

🅿️Closed Parking5
📅Completion2026-12-31
🏗️Proposed Floors17
Sanctioned17
🏗️Proposed Floors17
Sanctioned17
🅿️Closed Parking27
📅Completion2026-12-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk37.36000061035156000
0%
1Bhk37.709999084472656000
0%
1Bhk37.939998626708984000
0%
1Bhk38.790000915527344000
0%
2Bhk50.47999954223633000
0%
2Bhk53.880001068115234000
0%
Shop12.899999618530273000
0%
Shop15.0000
0%
Shop15.760000228881836000
0%
Shop16.979999542236328000
0%
Shop18.0000
0%

1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK37.3652052
0%
2 BHK50.48202
0%
2 BHK53.8830129
3%
Shop12.9202
0%
Shop15.0101
0%
Shop15.76202
0%
Shop16.98202
0%
Shop18.0404
0%

8

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK37.711203117
2%
1 BHK37.9428028
0%
1 BHK38.7930129
3%

Construction Progress

6

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 100%

8

Basement (if any)50%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth50%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.