Project Information

RERA Certificate No.
P51900010722
Registration No.
REA51900022050
Registration Date
2022-11-17
Developer
Sobhaniye Jp Developers Partnership
Architect
Concepts Infrastructure Consultants
Project Bank
ICICI BANK LIMITED
Proposed Possession
2021-12-31
Revised Possession
1900-01-01
Extended Possession
2025-05-30
Units Sold
0
Buildings
1
Project Area
2600.35 sq.m
Total FSI
11769.50
Approved FSI
11649.96
MahaRERA QR
Riddhi Siddhi Apartments Chs
MahaRERA — P51900010722
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors43
Sanctioned43
⬇️Basements1
🚗Open Parking8
🅿️Closed Parking101
📅Completion2021-12-31

Apartment Configurations

Riddhi Siddhi Apartments

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK48.68202
0%
1 BHK50.17101
0%
2 BHK65.31422
50%
2 BHK68.37110
100%
2 BHK DLX Type 174.6990
100%
3 BHK99.961138
27%
3 BHK DLX Type 1126.25110
100%
3 BHK DLX Type 2126.4414113
7%
Duplex143.63211
50%
Duplex153.57211
50%
Shop52.48110
100%

Construction Progress

Riddhi Siddhi Apartments

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises95%
Overall Percentage of Completion of the work done For the entire Building /Wing99%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises95%
Sanitary Fittings within the flats / premises95%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station100%
Energy management
Fire Protection And Fire Safety Requirements100%
Fitness Centre100%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal100%
Storm Water Drains100%
Street Lighting
Swimming Pool100%
Treatment And Disposal Of Sewage And Sullage Water100%
Water Conservation, Rain water Harvesting100%
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.