RERA: A51800043517

Rishabraj Agnel

by Rishabraj Estate Developers Pvt Ltd Company
Certificate SignedP51800030530

Project Information

RERA Certificate No.
P51800030530
Registration No.
REA51800093592
Registration Date
2021-08-30
Developer
Rishabraj Estate Developers Pvt Ltd Company
Architect
Abhijit Udani
Project Bank
AU SMALL FINANCE BANK LIMITED
Proposed Possession
2024-08-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
770.00 sq.m
Total FSI
2255.05
Approved FSI
823.57
MahaRERA QR
Rishabraj Agnel
MahaRERA — P51800030530
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors11
Sanctioned11
🚗Open Parking9
🅿️Closed Parking1
📅Completion2024-08-31

Apartment Configurations

Rishabraj Agnel

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK37.76651
83%
1 BHK38.89101
0%
1 BHK40.63642
67%
2 BHK51.98110
100%
2 BHK56.28422
50%
2 BHK59.62321
67%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk37.7599983215332000
0%
1Bhk38.88999938964844000
0%
1Bhk40.630001068115234000
0%
2Bhk51.97999954223633000
0%
2Bhk56.279998779296875000
0%
2Bhk59.619998931884766000
0%

Construction Progress

RISHABRAJ AGNEL

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Rishabraj Agnel

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space100%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station100%
Energy management
Fire Protection And Fire Safety Requirements100%
Landscaping & Tree Planting100%
Open Parking100%
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal100%
Storm Water Drains100%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting100%
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.