📞 +91 98200 30685✉️
RERA: A51800043517

Rishabraj Park Vistas

by H Rishabraj Realty Partnership
Certificate SignedP51800033442

Project Information

RERA Certificate No.
P51800033442
Registration No.
REA51800103388
Registration Date
2022-02-22
Developer
H Rishabraj Realty Partnership
Architect
Divyesh Parekh
Project Bank
HDFC BANK
Proposed Possession
2025-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
944.60 sq.m
Total FSI
2801.58
Approved FSI
2370.50
MahaRERA QR
Rishabraj Park Vistas
MahaRERA — P51800033442
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors14
Sanctioned14
🅿️Closed Parking47
📅Completion2025-12-31

Apartment Configurations

Rishabraj Park Vistas

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.77101
0%
1 BHK38.47505
0%
2 BHK65.52404
0%
2 BHK65.53202
0%
3 BHK103.25404
0%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk31.770000457763672000
0%
1Bhk38.470001220703125000
0%
2Bhk65.5199966430664000
0%
2Bhk65.52999877929688000
0%
3Bhk103.25000
0%

Construction Progress

RISHABRAJ PARK VISTAS

Basement (if any)0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Plinth0%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises10%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%

Rishabraj Park Vistas

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises50%
Overall Percentage of Completion of the work done For the entire Building /Wing65%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises10%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.80%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing60%
X number of Basement(s) and Plinth0%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Solid Waste Management And Disposal100%
Storm Water Drains20%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting30%
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.