Project Information

RERA Certificate No.
P51800010914
Registration No.
REA51800018423
Registration Date
2017-08-31
Developer
SANDU DEVELOPERS Partnership
Architect
Ashish Bhatt
Project Bank
HDFC BANK
Proposed Possession
2018-10-31
Revised Possession
2018-10-31
Extended Possession
2019-10-31
Units Sold
0
Buildings
1
Project Area
1267.90 sq.m
Total FSI
3401.00
Approved FSI
2898.53
MahaRERA QR
RUDRAKSH
MahaRERA — P51800010914
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors15
Sanctioned15
🚗Open Parking18
🅿️Closed Parking43
📅Completion2018-04-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
2Bhk 67.70999908447266 0 0 0
0%
2Bhk 69.61000061035156 0 0 0
0%
2Bhk 76.58000183105469 0 0 0
0%
2Bhk 78.41000366210938 0 0 0
0%
3Bhk 111.98999786376953 0 0 0
0%
Shop 180.69000244140625 0 0 0
0%

Rudraksh

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 67.71 7 5 2
71%
2 BHK 69.61 6 5 1
83%
2 BHK 76.58 4 4 0
100%
2 BHK 78.41 5 5 0
100%
3 BHK 111.99 11 8 3
73%
SHOP 180.69 1 1 0
100%

Construction Progress

RUDRAKSH

Basement (if any)100%

Rudraksh

Excavation100%

RUDRAKSH

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Rudraksh

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

RUDRAKSH

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Rudraksh

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

RUDRAKSH

Plinth100%
Podiums (if any) 100%

Rudraksh

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

RUDRAKSH

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Rudraksh

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

RUDRAKSH

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Rudraksh

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 100%
Storm Water Drains 100%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 100%
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.