SHREE SARASWATI CHS LTD PLOT 8B
by NAV DURGA CONSTRUCTION COMPANY
Partnership
Project Information
RERA Certificate No.
P51800017436
Registration No.
REA51800041595
Registration Date
2021-09-09
Developer
NAV DURGA CONSTRUCTION COMPANY Partnership
Architect
B H Wadhwa & Co
Project Bank
YES BANK
Proposed Possession
2023-12-30
Revised Possession
1900-01-01
Extended Possession
2025-03-31
Units Sold
0
Buildings
1
Project Area
11541.28 sq.m
Total FSI
5794.00
Approved FSI
3927.00
SHREE SARASWATI CHS LTD PLOT 8B
MahaRERA — P51800017436
MahaRERA — P51800017436
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors17
✅Sanctioned17
🚗Open
Parking41
🅿️Closed Parking34
📅Completion2022-12-31
Apartment Configurations
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| Bldg A1 2Bhk | 69.83999633789062 | 0 | 0 | 0 | 0% |
| Bldg. B6 2Bhk | 58.95000076293945 | 0 | 0 | 0 | 0% |
| Bldg.A1.2Bhk | 70.16999816894531 | 0 | 0 | 0 | 0% |
| Bldg.A1.3Bhk | 81.5 | 0 | 0 | 0 | 0% |
| Bldg.B6.3Bhk | 69.0999984741211 | 0 | 0 | 0 | 0% |
Shree Saraswati Chs Ltd Bldg B6 And A1
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| BLDG A1 2BHK | 69.84 | 24 | 20 | 4 | 83% |
| BLDG. B6 2BHK | 58.95 | 40 | 34 | 6 | 85% |
| BLDG.A1.2 BHK | 70.17 | 13 | 11 | 2 | 85% |
| BLDG.A1.3 BHK | 81.5 | 1 | 1 | 0 | 100% |
| BLDG.B6.3 BHK | 69.1 | 1 | 1 | 0 | 100% |
Construction Progress
SHREE SARASWATI CHS LTD BLDG B6 AND A1
Shree Saraswati Chs Ltd Bldg B6 And A1
SHREE SARASWATI CHS LTD BLDG B6 AND A1
Shree Saraswati Chs Ltd Bldg B6 And A1
SHREE SARASWATI CHS LTD BLDG B6 AND A1
Shree Saraswati Chs Ltd Bldg B6 And A1
SHREE SARASWATI CHS LTD BLDG B6 AND A1
Shree Saraswati Chs Ltd Bldg B6 And A1
SHREE SARASWATI CHS LTD BLDG B6 AND A1
Shree Saraswati Chs Ltd Bldg B6 And A1
SHREE SARASWATI CHS LTD BLDG B6 AND A1
Shree Saraswati Chs Ltd Bldg B6 And A1
RERA Registered Amenities
✅
Aggregate area of recreational Open Space
✅
CLUB HOUSE
✅
Community Buildings
✅
Electrical Meter Room, Sub-Station, Receiving Station
⬜
Energy management
✅
Fire Protection And Fire Safety
Requirements
✅
GYM
✅
Landscaping & Tree Planting
25%
✅
Open Parking
✅
Sewerage (Chamber, Lines, Septic Tank , STP)
5%
✅
Solid Waste Management And Disposal
✅
Storm Water Drains
✅
Street Lighting
✅
Treatment And Disposal Of Sewage And Sullage Water
20%
✅
Water Conservation, Rain water Harvesting
✅