Sagar Avenue Ii Ef

by Sagar Shopping Developers Partnership
Certificate SignedP51800012870

Project Information

RERA Certificate No.
P51800012870
Registration No.
REA51800022687
Registration Date
2021-09-09
Developer
Sagar Shopping Developers Partnership
Architect
Hemant Parikh & Associates
Project Bank
CANARA BANK
Proposed Possession
2023-06-01
Revised Possession
2023-06-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
8703.45 sq.m
Total FSI
8703.45
Approved FSI
8543.45
MahaRERA QR
Sagar Avenue Ii Ef
MahaRERA — P51800012870
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors15
Sanctioned15
🚗Open Parking3
🅿️Closed Parking1
📅Completion1900-01-01

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 Bhk37.900001525878906000
0%
1 Bhk50.7400016784668000
0%
1 Bhk59.470001220703125000
0%
2 Bhk58.25000
0%
2 Bhk64.19999694824219000
0%
2 Bhk74.13999938964844000
0%
2 Bhk80.63999938964844000
0%
2 Bhk80.81999969482422000
0%
3 Bhk78.5000
0%
3 Bhk98.01000213623047000
0%

Wing E, F

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK37.9101
0%
1 BHK50.741495
64%
1 BHK59.4710010
0%
2 BHK58.2514122
86%
2 BHK64.2303
0%
2 BHK74.141028
20%
2 BHK80.6420155
75%
2 BHK80.8215213
13%
3 BHK78.5101
0%
3 BHK98.011248
33%

Construction Progress

Wing E, F

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises95%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises95%
Sanitary Fittings within the flats / premises95%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing98%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station100%
Energy management
Fire Protection And Fire Safety Requirements100%
Landscaping & Tree Planting
Open Parking100%
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal100%
Storm Water Drains100%
Street Lighting100%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting100%
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.