RERA: A51800043517

Sai Anand Plaza

by Shree Sai Developers Partnership
Certificate SignedP51700033362

Project Information

RERA Certificate No.
P51700033362
Registration No.
REA51700101434
Registration Date
2022-02-16
Developer
Shree Sai Developers Partnership
Architect
Bac Planners And Engineers
Project Bank
BANK OF BARODA
Proposed Possession
2023-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
9
Units Sold
8 (89%)
Buildings
1
Project Area
617.85 sq.m
Total FSI
3021.03
Approved FSI
3021.03
MahaRERA QR
Sai Anand Plaza
MahaRERA — P51700033362
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors12
Sanctioned12
⬇️Basements1
🅿️Closed Parking1
📅Completion2023-12-31

Apartment Configurations

Sai Anand Plaza

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK36.25101
0%
2 BHK63.55404
0%
3 BHK81.85404
0%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk36.25000
0%
2Bhk63.54999923706055000
0%
3Bhk81.8499984741211000
0%

Construction Progress

SAI ANAND PLAZA

Basement (if any)65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.73%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Plinth65%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises65%
Slabs of Super Structure65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%

Sai Anand Plaza

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate73%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises65%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises65%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.85%
Stilt Floor65%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing65%
X number of Basement(s) and Plinth65%
X number of Podiums0%
X number of Slabs of Super Structure65%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station100%
Energy management
Fire Protection And Fire Safety Requirements75%
Landscaping & Tree Planting100%
Open Parking100%
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal
Storm Water Drains100%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting100%
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.