📞 +91 98200 30685✉️
RERA: A51800043517

SAI PRASAD GARDEN- PHASE 1

by SAI PRASAD ENTERPRISES Partnership
Certificate SignedP52000000694

Project Information

RERA Certificate No.
P52000000694
Registration No.
REA52000004665
Registration Date
2021-09-09
Developer
SAI PRASAD ENTERPRISES Partnership
Project Bank
AXIS BANK
Proposed Possession
2021-12-22
Revised Possession
2021-12-22
Extended Possession
2025-12-31
Units Sold
0
Buildings
4
Project Area
3761.00 sq.m
Total FSI
3761.71
Approved FSI
1677.71
MahaRERA QR
SAI PRASAD GARDEN- PHASE 1
MahaRERA — P52000000694
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors5
Sanctioned5
🅿️Closed Parking42
📅Completion2020-12-22
🏗️Proposed Floors5
Sanctioned5
🅿️Closed Parking42
📅Completion2020-12-22
🏗️Proposed Floors5
Sanctioned5
🅿️Closed Parking42
📅Completion2020-12-22
🏗️Proposed Floors5
Sanctioned5
🅿️Closed Parking68
📅Completion2020-12-22

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk24.709999084472656000
0%
1Bhk29.920000076293945000
0%
1Bhk30.100000381469727000
0%
1Bhk30.110000610351562000
0%
1Bhk35.54999923706055000
0%
1Bhk38.91999816894531000
0%
1Bhk40.7400016784668000
0%

Building No- 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK24.71330
100%
1 BHK29.92101
0%
1 BHK30.1202
0%
1 BHK30.11101
0%
1RK10.91220
100%
1RK11.0770
100%

Building No- 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.1202
0%
1 BHK30.11202
0%
1RK10.91440
100%
1RK11.0880
100%

Building No- 3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK10.91440
100%
1 BHK30.1202
0%
1 BHK30.11202
0%
1RK11.0880
100%

Building No- 4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK38.92202
0%
1 BHK40.74202
0%
1RK11.76880
100%
1RK11.86440
100%

Construction Progress

BUILDING NO- 1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

BUILDING NO- 2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

BUILDING NO- 3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

BUILDING NO- 4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station100%
Energy management100%
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal
Storm Water Drains100%
Street Lighting100%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting100%
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.