Sanghvi Heights Phase 2

by Sanghvi Premises Private Limited Company
Certificate Signed P51900026345
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51900026345
Registration No.
REA51900076054
Registration Date
2021-09-08
Developer
Sanghvi Premises Private Limited Company
Architect
Ms Vision Architects
Project Bank
AU SMALL FINANCE BANK LIMITED
Proposed Possession
2024-06-30
Revised Possession
1900-01-01
Extended Possession
2025-06-30
Total Units
31
Units Sold
19 (61%)
Buildings
1
Project Area
2934.60 sq.m
Total FSI
2951.21
Approved FSI
2435.72
MahaRERA QR
Sanghvi Heights Phase 2
MahaRERA — P51900026345
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors8
Sanctioned8
🏠Habitable8
🔢Total Units31
🏡Residential31
🅿️Closed Parking19
📅Completion2023-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
2Bhk 48.34000015258789 0 0 0
0%
2Bhk 54.95000076293945 0 0 0
0%
2Bhk 54.9900016784668 0 0 0
0%
2Bhk 56.0 0 0 0
0%
2Bhk 59.150001525878906 0 0 0
0%
3Bhk 70.56999969482422 0 0 0
0%
3Bhk 78.44999694824219 0 0 0
0%
Refuge 0 0 0
0%

Sanghvi Heights Phase 2

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 48.34 1 1 0
100%
2 BHK 54.95 7 1 6
14%
2 BHK 54.99 7 1 6
14%
2 BHK 56.0 7 3 4
43%
2 BHK 59.15 1 1 0
100%
3 BHK 70.57 1 1 0
100%
3 BHK 78.45 7 3 4
43%
Refuge 1 0 1
0%

Construction Progress

Sanghvi Heights Phase 2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate71%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.71%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing95%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management 100%
Fire Protection And Fire Safety Requirements 81%
Landscaping & Tree Planting 100%
Open Parking 20%
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 100%
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 100%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.