Project Information

RERA Certificate No.
P51900005890
Registration No.
REA51900013527
Registration Date
2017-08-14
Developer
Concrete Lifestyles & Infrastructure Private Limited Company
Architect
Consultant Combined Architects
Proposed Possession
2020-04-30
Revised Possession
2020-04-30
Extended Possession
2022-06-30
Total Units
1
Units Sold
0 (0%)
Buildings
1
Project Area
411.84 sq.m
Total FSI
1562.97
Approved FSI
1235.52
MahaRERA QR
Santosh Building
MahaRERA — P51900005890
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors20
Sanctioned20
🚗Open Parking3
🅿️Closed Parking1
📅Completion2020-04-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
2 Bhk 73.7699966430664 0 0 0
0%

Santosh Building

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 73.77 21 10 11
48%

Construction Progress

NA Plot Without Structure

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

SANTOSH BUILDING

Basement (if any)100%

Santosh Building

Excavation100%

SANTOSH BUILDING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Santosh Building

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

SANTOSH BUILDING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Santosh Building

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

SANTOSH BUILDING

Plinth100%
Podiums (if any) 100%

Santosh Building

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

SANTOSH BUILDING

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Santosh Building

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

SANTOSH BUILDING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Santosh Building

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 100%
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.