💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800012064
Registration No.
REA51800017545
Registration Date
2017-09-01
Developer
Siroya Developers Pvt Ltd Company
Architect
Swapnil D Sawant Ms Set Square Architects
Project Bank
YES BANK
Proposed Possession
2019-12-31
Revised Possession
2019-12-31
Extended Possession
2024-12-30
Units Sold
0
Buildings
1
Project Area
831.70 sq.m
Total FSI
2245.55
Approved FSI
1102.25
MahaRERA QR
Saptashringi
MahaRERA — P51800012064
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors11
Sanctioned11
🅿️Closed Parking1
📅Completion1900-01-01

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 38.119998931884766 0 0 0
0%
1Bhk 39.72999954223633 0 0 0
0%
2.5Bhk 69.04000091552734 0 0 0
0%
2Bhk 58.34000015258789 0 0 0
0%
2Bhk 59.91999816894531 0 0 0
0%
2Bhk 60.88999938964844 0 0 0
0%
Type 1 6.039999961853027 0 0 0
0%
Type2 27.8700008392334 0 0 0
0%
Type3 28.059999465942383 0 0 0
0%
Type4 21.829999923706055 0 0 0
0%

Saptashringi

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 38.12 1 1 0
100%
1 BHK 39.73 4 1 3
25%
2 BHK 58.34 3 3 0
100%
2 BHK 59.92 5 5 0
100%
2 BHK 60.89 1 0 1
0%
2.5 BHK 69.04 1 0 1
0%
Type 1 6.04 2 2 0
100%
Type2 27.87 1 1 0
100%
Type3 28.06 1 1 0
100%
Type4 21.83 1 1 0
100%

Construction Progress

Saptashringi

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises4%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises4%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure50%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
Stilt Floor75%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure50%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal 50%
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.