Season Sahara Building No 4 And 5

by Samarth Sai Builders & Developers Partnership
Certificate SignedP51700031568

Project Information

RERA Certificate No.
P51700031568
Registration No.
REA51700096157
Registration Date
2023-08-14
Developer
Samarth Sai Builders & Developers Partnership
Architect
De Con Consultants
Project Bank
AXIS BANK
Proposed Possession
2025-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
399
Units Sold
319 (80%)
Buildings
2
Project Area
4230.00 sq.m
Total FSI
21553.19
Approved FSI
21553.19
MahaRERA QR
Season Sahara Building No 4 And 5
MahaRERA — P51700031568
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors23
Sanctioned23
🏠Habitable22
🔢Total Units168
🏡Residential168
📅Completion2025-12-31
🏗️Proposed Floors23
Sanctioned23
🏠Habitable22
🔢Total Units231
🏡Residential231
📅Completion2025-12-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk28.549999237060547000
0%
1Bhk28.850000381469727000
0%
1Bhk29.139999389648438000
0%
1Bhk29.690000534057617000
0%
1Bhk29.84000015258789000
0%
1Bhk32.31999969482422000
0%
1Bhk32.90999984741211000
0%
1Bhk33.0000
0%
1Bhk33.40999984741211000
0%
1Bhk34.150001525878906000
0%
2Bhk39.150001525878906000
0%
2Bhk39.70000076293945000
0%
2Bhk39.84000015258789000
0%
2Bhk39.970001220703125000
0%
2Bhk44.599998474121094000
0%
2Bhk44.7599983215332000
0%
2Bhk44.939998626708984000
0%
2Bhk47.11000061035156000
0%
2Bhk47.18000030517578000
0%

Season Sahara Building No 4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.1422319
14%
1 BHK29.6922220
9%
1 BHK29.84221012
45%
1 BHK32.9120155
75%
1 BHK33.4120182
90%
1 BHK34.1520182
90%
2 BHK44.620200
100%
2 BHK47.1122814
36%

Season Sahara Building No 5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK28.0820020
0%
1 BHK28.55603822
63%
1 BHK28.85604020
67%
1 BHK32.32101
0%
1 BHK33.0532
60%
2 BHK39.1520515
25%
2 BHK39.720713
35%
2 BHK39.8420182
90%
2 BHK39.97401129
28%
2 BHK44.76202
0%
2 BHK44.94202
0%
2 BHK47.18110
100%

Construction Progress

SEASON SAHARA BUILDING NO 4

Basement (if any)100%

Season Sahara Building No 4

Excavation100%

SEASON SAHARA BUILDING NO 4

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%

Season Sahara Building No 4

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

SEASON SAHARA BUILDING NO 4

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%

Season Sahara Building No 4

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises75%
Overall Percentage of Completion of the work done For the entire Building /Wing65%

SEASON SAHARA BUILDING NO 4

Plinth100%
Podiums (if any) 100%

Season Sahara Building No 4

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises35%

SEASON SAHARA BUILDING NO 4

Sanitary Fittings within the flats / premises70%
Slabs of Super Structure100%

Season Sahara Building No 4

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.25%

SEASON SAHARA BUILDING NO 4

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks55%

Season Sahara Building No 4

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing15%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

SEASON SAHARA BUILDING NO 5

Basement (if any)100%

Season Sahara Building No 5

Excavation100%

SEASON SAHARA BUILDING NO 5

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%

Season Sahara Building No 5

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

SEASON SAHARA BUILDING NO 5

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%

Season Sahara Building No 5

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises75%
Overall Percentage of Completion of the work done For the entire Building /Wing65%

SEASON SAHARA BUILDING NO 5

Plinth100%
Podiums (if any) 100%

Season Sahara Building No 5

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises35%

SEASON SAHARA BUILDING NO 5

Sanitary Fittings within the flats / premises70%
Slabs of Super Structure100%

Season Sahara Building No 5

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.25%

SEASON SAHARA BUILDING NO 5

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks55%

Season Sahara Building No 5

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing15%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.