RERA: A51800043517

Serene Shelter

by Buildtech Group Partnership
Certificate SignedP51800009965
šŸ’¬ WhatsAppšŸ“ž Call

Project Information

RERA Certificate No.
P51800009965
Registration No.
REA51800021182
Registration Date
2021-09-09
Developer
Buildtech Group Partnership
Architect
Ketan Vaidya Associates
Project Bank
ICICI BANK LIMITED
Proposed Possession
2024-12-30
Revised Possession
2024-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
5112.20 sq.m
Total FSI
18946.07
Approved FSI
18946.07
MahaRERA QR
Serene Shelter
MahaRERA — P51800009965
Scan to verify on MahaRERA portal

Wing-wise Details

šŸ—ļøProposed Floors18
āœ…Sanctioned18
ā¬‡ļøBasements1
šŸ“…Completion1900-01-01

Apartment Configurations

Buildtech Group

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK43.4848480
100%
2 BHK60.2924240
100%
2 BHK66.7924240
100%
2 BHK68.224240
100%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk43.47999954223633000
0%
2Bhk60.290000915527344000
0%
2Bhk66.79000091552734000
0%
2Bhk68.19999694824219000
0%

Construction Progress

BUILDTECH GROUP

Basement (if any)10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.43%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises44%
Plinth10%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure44%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks44%

Buildtech Group

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises44%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.44%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing43%
X number of Basement(s) and Plinth10%
X number of Podiums0%
X number of Slabs of Super Structure44%

RERA Registered Amenities

āœ…Aggregate area of recreational Open Space
⬜Community Buildings
āœ…Electrical Meter Room, Sub-Station, Receiving Station
⬜Energy management
āœ…Fire Protection And Fire Safety Requirements
āœ…Landscaping & Tree Planting
⬜Open Parking
āœ…Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
āœ…Storm Water Drains
āœ…Street Lighting
āœ…Treatment And Disposal Of Sewage And Sullage Water
āœ…Water Conservation, Rain water Harvesting
āœ…Water Supply
CallWhatsApp
āœ‰ļø

Get in Touch

Our team will connect with you shortly

+91
šŸ”’ Your details are secure with us
⚔ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
šŸ‘‹ Looking for the right project? Let me help you find it!
šŸ—ļø
MPE Project Advisor
ā— Online now