RERA: A51800043517

Sheetal Complex Wing D E

by Abhay Builders
Kept in Abeyance P51700012936
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700012936
Registration No.
REA51700022778
Developer
Abhay Builders
Architect
Chetan U Sarvaiya
Project Bank
DCB Bank
Proposed Possession
2018-08-05
Revised Possession
2021-02-05
Extended Possession
1900-01-01
Buildings
2
Project Area
7890.00 sq.m
Total FSI
4905.61
Litigations
⚠️ Yes
MahaRERA QR
Sheetal Complex Wing D E
MahaRERA — P51700012936
Scan to verify on MahaRERA portal

Wing-wise Details

🅿️Closed Parking1
📅Completion1900-01-01
🅿️Closed Parking10
📅Completion1900-01-01

Apartment Configurations

Sheetal Complex Wing E

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 47.0 55 46 9
84%

Shteel Complex Wing D

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 35.0 27 26 1
96%
2 BHK 46.0 13 13 0
100%

Construction Progress

Sheetal Complex Wing E

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate20%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing79%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.80%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Shteel Complex Wing D

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate20%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing79%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.80%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 30%
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting 40%
Open Parking 50%
Sewerage (Chamber, Lines, Septic Tank , STP) 50%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.