📞 +91 98200 30685 ✉️
RERA: A51800043517

AVANTE

by Sanjeevani Vyapaar LLP Partnership
Certificate Signed P51800001140
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800001140
Registration No.
REA51800005659
Registration Date
2022-11-21
Developer
Sanjeevani Vyapaar LLP Partnership
Architect
Sandeep Shikre & Associates
Project Bank
INDUSIND BANK
Proposed Possession
2022-12-30
Revised Possession
2022-12-30
Extended Possession
2024-12-31
Units Sold
0
Buildings
3
Project Area
7306.60 sq.m
Total FSI
24287.44
Approved FSI
5568.58
MahaRERA QR
AVANTE
MahaRERA — P51800001140
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors31
Sanctioned31
⬇️Basements1
🅿️Closed Parking146
📅Completion2021-12-31
🏗️Proposed Floors30
Sanctioned30
⬇️Basements1
🅿️Closed Parking111
📅Completion2021-12-31
🏗️Proposed Floors30
Sanctioned30
⬇️Basements1
🅿️Closed Parking126
📅Completion2021-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 41.150001525878906 0 0 0
0%
1Bhk 41.15999984741211 0 0 0
0%
1Bhk 41.2599983215332 0 0 0
0%
1Bhk 41.31999969482422 0 0 0
0%
1Bhk 41.72999954223633 0 0 0
0%
1Bhk 44.119998931884766 0 0 0
0%
2Bhk 50.650001525878906 0 0 0
0%
2Bhk 50.75 0 0 0
0%
2Bhk 50.81999969482422 0 0 0
0%
2Bhk 51.459999084472656 0 0 0
0%
2Bhk 51.529998779296875 0 0 0
0%
2Bhk 68.38999938964844 0 0 0
0%
2Bhk 68.43000030517578 0 0 0
0%
2Bhk 68.63999938964844 0 0 0
0%
3.5Bhk 89.29000091552734 0 0 0
0%
3Bhk 79.7699966430664 0 0 0
0%
5Bhk &Amp; More 138.1300048828125 0 0 0
0%
Shop 118.69999694824219 0 0 0
0%
Shop 121.5999984741211 0 0 0
0%
Shop 158.49000549316406 0 0 0
0%

Wing A

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 41.16 50 50 0
100%
1 BHK 41.32 25 25 0
100%
2 BHK 50.65 21 21 0
100%
2 BHK 50.75 25 25 0
100%
2 BHK 51.46 25 25 0
100%

Wing B

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 41.15 20 20 0
100%
1 BHK 41.26 24 24 0
100%
1 BHK 41.73 24 23 1
96%
2 BHK 50.82 24 24 0
100%
2 BHK 51.53 24 23 1
96%
2 BHK 68.39 24 24 0
100%

Wing C

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 44.12 1 1 0
100%
2 BHK 68.43 24 23 1
96%
2 BHK 68.64 24 23 1
96%
3 BHK 79.77 41 40 1
98%
3.5 BHK 89.29 3 3 0
100%
5 BHK & more 138.13 1 1 0
100%
Shop 118.7 1 1 0
100%
Shop 121.6 1 1 0
100%
Shop 158.49 1 1 0
100%

Construction Progress

WING A

Basement (if any)100%

Wing A

Excavation100%

WING A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Wing A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

WING A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%

Wing A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises60%
Overall Percentage of Completion of the work done For the entire Building /Wing60%

WING A

Plinth100%
Podiums (if any) 85%

Wing A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING A

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Wing A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.75%

WING A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%

Wing A

Stilt Floor80%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums85%
X number of Slabs of Super Structure100%

WING B

Basement (if any)100%

Wing B

Excavation100%

WING B

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Wing B

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

WING B

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%

Wing B

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises60%
Overall Percentage of Completion of the work done For the entire Building /Wing60%

WING B

Plinth100%
Podiums (if any) 85%

Wing B

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING B

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Wing B

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.75%

WING B

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%

Wing B

Stilt Floor80%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums85%
X number of Slabs of Super Structure100%

WING C

Basement (if any)100%

Wing C

Excavation100%

WING C

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Wing C

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

WING C

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Wing C

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%

WING C

Plinth100%
Podiums (if any) 85%

Wing C

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING C

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure5%

Wing C

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.12%

WING C

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks12%

Wing C

Stilt Floor80%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums85%
X number of Slabs of Super Structure5%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
FITNESS CENTRE
KIDS PLAY AREA
Landscaping & Tree Planting
MULTI PURPOSE COURT
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 20%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
SWIMING POOL
Treatment And Disposal Of Sewage And Sullage Water 60%
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.