📞 +91 98200 30685 ✉️
RERA: A51800043517

Shreeji Aspire

by Shreeji Construction Partnership
Certificate Signed P51800003919
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800003919
Registration No.
REA51800011498
Registration Date
2017-12-07
Developer
Shreeji Construction Partnership
Project Bank
AXIS BANK
Proposed Possession
2020-11-30
Revised Possession
2020-11-30
Extended Possession
2022-11-28
Units Sold
0
Buildings
1
Project Area
2054.02 sq.m
Total FSI
8152.00
Approved FSI
8152.00
MahaRERA QR
Shreeji Aspire
MahaRERA — P51800003919
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors24
Sanctioned24
🅿️Closed Parking54
📅Completion2022-11-28

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
Shop No 11 20.719999313354492 0 0 0
0%
Shop No 14 29.729999542236328 0 0 0
0%
Shop No 21 20.899999618530273 0 0 0
0%
Type 1 53.54999923706055 0 0 0
0%
Type 2 41.060001373291016 0 0 0
0%
Type3 40.560001373291016 0 0 0
0%

Composite Building 1

Type Carpet (sq.ft) Total Booked Available Status
Shop No 11 20.72 1 1 0
100%
Shop No 14 29.73 1 1 0
100%
Shop No 21 20.9 1 1 0
100%
Type 1 53.55 38 37 1
97%
Type 2 41.06 40 37 3
92%
Type3 40.56 20 15 5
75%

Construction Progress

Composite Building 1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 100%
Community Buildings
COVERED CAR PARK 100%
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management 100%
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 100%
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 100%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.