Siddharth Enclave

by Siddharth Developers Partnership
Certificate Signed P51900001979
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51900001979
Registration No.
REA51900011749
Registration Date
2025-10-28
Developer
Siddharth Developers Partnership
Architect
Ms Wairkar And Associates
Project Bank
HDFC BANK
Proposed Possession
2019-12-31
Revised Possession
2019-12-31
Extended Possession
2025-06-30
Total Units
68
Units Sold
64 (94%)
Buildings
2
Project Area
2321.93 sq.m
Total FSI
7356.96
Approved FSI
7131.91
MahaRERA QR
Siddharth Enclave
MahaRERA — P51900001979
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors16
Sanctioned16
🏠Habitable12
🔢Total Units58
🏡Residential58
🚗Open Parking3
🅿️Closed Parking25
📅Completion2019-12-31
🏗️Proposed Floors10
Sanctioned10
🏠Habitable6
🔢Total Units10
🏡Residential10
🚗Open Parking3
🅿️Closed Parking7
📅Completion2020-12-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 31.309999465942383 0 0 0
0%
1Bhk 33.95000076293945 0 0 0
0%
1Bhk 34.040000915527344 0 0 0
0%
2Bhk 48.790000915527344 0 0 0
0%

B Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 33.95 12 10 2
83%
1 BHK 34.04 44 41 3
93%

C Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 31.31 6 5 1
83%
2 BHK 48.79 6 6 0
100%

Construction Progress

B Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises95%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises95%
Sanitary Fittings within the flats / premises95%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
Stilt Floor97%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing95%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

C Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing88%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises95%
Sanitary Fittings within the flats / premises95%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
Stilt Floor97%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing98%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 97%
Energy management
Fire Protection And Fire Safety Requirements 95%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 98%
Solid Waste Management And Disposal
Storm Water Drains 98%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 90%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.