RERA: A51800043517

Skyper

by Qureshi Builders
Kept in Abeyance P51800013435
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800013435
Registration No.
REA51800023780
Developer
Qureshi Builders
Project Bank
ORIENTAL BANK OF COMMERCE
Proposed Possession
2022-12-30
Revised Possession
2023-12-30
Extended Possession
1900-01-01
Buildings
3
Project Area
1567.00 sq.m
Total FSI
2745.00
Approved FSI
245.00
MahaRERA QR
Skyper
MahaRERA — P51800013435
Scan to verify on MahaRERA portal

Wing-wise Details

📅Completion1900-01-01
📅Completion1900-01-01
⬇️Basements1
🚗Open Parking3
📅Completion1900-01-01

Apartment Configurations

Skyper

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 41.45 3 3 0
100%
4 BHK 155.02 2 2 0
100%
4 BHK 160.78 1 1 0
100%
4 BHK 162.64 12 1 11
8%

Skyper B

Type Carpet (sq.ft) Total Booked Available Status
MARKET 384.0 1 1 0
100%

Skyper C

Type Carpet (sq.ft) Total Booked Available Status
RESIDENTIAL 1035.0 30 0 30
0%

Construction Progress

Skyper

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate97%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises99%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor1%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums2%
X number of Slabs of Super Structure19%

Skyper B

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate90%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.96%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing96%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

Skyper C

Excavation0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space 100%
Community Buildings 10%
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management 80%
Fire Protection And Fire Safety Requirements 95%
Landscaping & Tree Planting 100%
LIFT STAIRCASE TERRACE 70%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 60%
Storm Water Drains 100%
Street Lighting 10%
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 10%
Water Supply 70%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.