THE SOLARIS
by SOSAR ENTERPRISES
Partnership
Project Information
RERA Certificate No.
P51800051256
Registration No.
REA51800138860
Registration Date
2023-06-08
Developer
SOSAR ENTERPRISES Partnership
Architect
Priyank Bhatt
Project Bank
KOTAK MAHINDRA BANK LIMITED
Proposed Possession
2026-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
735.80 sq.m
Total FSI
2251.55
Approved FSI
715.55
THE SOLARIS
MahaRERA — P51800051256
MahaRERA — P51800051256
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors9
✅Sanctioned9
🅿️Closed Parking13
📅Completion2026-12-31
Apartment Configurations
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 2Bhk | 14.859999656677246 | 0 | 0 | 0 | 0% |
| 2Bhk | 18.389999389648438 | 0 | 0 | 0 | 0% |
| 2Bhk | 27.8700008392334 | 0 | 0 | 0 | 0% |
| 2Bhk | 64.37999725341797 | 0 | 0 | 0 | 0% |
| 2Bhk | 64.41000366210938 | 0 | 0 | 0 | 0% |
| 3Bhk | 87.79000091552734 | 0 | 0 | 0 | 0% |
| 3Bhk | 87.83000183105469 | 0 | 0 | 0 | 0% |
| Office Space | 46.93000030517578 | 0 | 0 | 0 | 0% |
| Shop | 6.96999979019165 | 0 | 0 | 0 | 0% |
| Shop | 34.11000061035156 | 0 | 0 | 0 | 0% |
The Solaris
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 2 BHK 202 | 70.57 | 1 | 0 | 1 | 0% |
| 3 BHK 203 | 87.76 | 1 | 0 | 1 | 0% |
| Office 101 | 72.61 | 1 | 0 | 1 | 0% |
| Office 102 | 69.29 | 1 | 0 | 1 | 0% |
| Office 103 | 46.92 | 1 | 0 | 1 | 0% |
| Office 104 | 32.2 | 1 | 0 | 1 | 0% |
| Office Ground Floor | 30.79 | 1 | 0 | 1 | 0% |
| Shop 1 | 25.03 | 1 | 0 | 1 | 0% |
| Shop 2 | 37.41 | 1 | 0 | 1 | 0% |
| Shop 3 | 29.18 | 1 | 0 | 1 | 0% |
| Shop 4 | 33.96 | 1 | 0 | 1 | 0% |
Construction Progress
THE SOLARIS
The Solaris
THE SOLARIS
The Solaris
THE SOLARIS
The Solaris
THE SOLARIS
The Solaris
THE SOLARIS
The Solaris
THE SOLARIS
The Solaris
RERA Registered Amenities
⬜
Aggregate area of recreational Open Space
⬜
Community Buildings
✅
Electrical Meter Room, Sub-Station, Receiving Station
⬜
Energy management
✅
Fire Protection And Fire Safety
Requirements
✅
Landscaping & Tree Planting
⬜
Open Parking
✅
Sewerage (Chamber, Lines, Septic Tank , STP)
80%
✅
Solid Waste Management And Disposal
✅
Storm Water Drains
⬜
Street Lighting
⬜
Treatment And Disposal Of Sewage And Sullage Water
✅
Water Conservation, Rain water Harvesting
50%
✅