Laxmi Niwas
by Sugee Eight Developers Llp
Others
Project Information
RERA Certificate No.
P51900019608
Registration No.
REA51900049553
Registration Date
2021-09-09
Developer
Sugee Eight Developers Llp Others
Architect
Anil Patil
Project Bank
AU SMALL FINANCE BANK LIMITED
Proposed Possession
2022-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
454.67 sq.m
Total FSI
2971.11
Approved FSI
2700.28
Laxmi Niwas
MahaRERA — P51900019608
MahaRERA — P51900019608
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors22
✅Sanctioned22
📅Completion2021-12-31
Apartment Configurations
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1Bhk | 44.099998474121094 | 0 | 0 | 0 | 0% |
| 2Bhk | 67.93000030517578 | 0 | 0 | 0 | 0% |
| Commercial | 149.41000366210938 | 0 | 0 | 0 | 0% |
| Shop | 25.760000228881836 | 0 | 0 | 0 | 0% |
Laxmi Niwas
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 44.1 | 6 | 3 | 3 | 50% |
| 2 BHK | 67.93 | 7 | 2 | 5 | 29% |
| Commercial | 149.41 | 1 | 1 | 0 | 100% |
| Shop | 25.76 | 1 | 1 | 0 | 100% |
Construction Progress
Laxmi Niwas
RERA Registered Amenities
⬜
Aggregate area of recreational Open Space
⬜
Community Buildings
✅
Electrical Meter Room, Sub-Station, Receiving Station
50%
⬜
Energy management
✅
Fire Protection And Fire Safety
Requirements
10%
⬜
Landscaping & Tree Planting
⬜
Open Parking
✅
Sewerage (Chamber, Lines, Septic Tank , STP)
100%
✅
Solid Waste Management And Disposal
✅
Storm Water Drains
⬜
Street Lighting
⬜
Treatment And Disposal Of Sewage And Sullage Water
✅
Water Conservation, Rain water Harvesting
100%
✅
Water Supply