📞 +91 98200 30685 ✉️
RERA: A51800043517

Sumer Trinity Vertical Phase-I

by Sumer Builders Partnership
Certificate Signed P51900017371
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51900017371
Registration No.
REA51900041572
Registration Date
2020-06-20
Developer
Sumer Builders Partnership
Architect
Ar Purvi Somaya
Project Bank
YES BANK
Proposed Possession
2023-06-30
Revised Possession
2023-06-30
Extended Possession
2024-06-30
Units Sold
0
Buildings
1
Project Area
2339.00 sq.m
Total FSI
18606.76
Approved FSI
5856.76
MahaRERA QR
Sumer Trinity Vertical Phase-I
MahaRERA — P51900017371
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors37
Sanctioned37
⬇️Basements3
🅿️Closed Parking138
📅Completion2022-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
4Bhk 274.239990234375 0 0 0
0%
4Bhk 275.4200134277344 0 0 0
0%
4Bhk 290.5400085449219 0 0 0
0%
4Bhk 290.6300048828125 0 0 0
0%
4Bhk 294.6199951171875 0 0 0
0%
4Bhk 294.7900085449219 0 0 0
0%
5Bhk 388.67999267578125 0 0 0
0%
5Bhk 392.510009765625 0 0 0
0%
5Bhk 418.0400085449219 0 0 0
0%

Vertical

Type Carpet (sq.ft) Total Booked Available Status
4 BHK 274.24 15 2 13
13%
4 BHK 275.42 15 2 13
13%
4 BHK 290.54 1 0 1
0%
4 BHK 290.63 1 0 1
0%
4 BHK 294.62 9 1 8
11%
4 BHK 294.79 9 3 6
33%
5 BHK 388.68 2 0 2
0%
5 BHK 392.51 1 0 1
0%
5 BHK 418.04 2 0 2
0%

Construction Progress

Vertical

Basement (if any)70%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Plinth70%
Podiums (if any) 50%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure45%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth70%
X number of Podiums50%
X number of Slabs of Super Structure45%

RERA Registered Amenities

36 Seater Lounge theater in Club House 100%
6 Guest Rooms in Club House 100%
Aggregate area of recreational Open Space
Amber Terrace in Club House 100%
Amphitheater
CCTV Cameras in Public Area
Club House 100%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 75%
Energy management
Fire Protection And Fire Safety Requirements
Gymnasium in Club House 100%
Kids Bubble and Slide pool in Layout 100%
Kids play area in Layout 100%
Landscaping & Tree Planting 60%
Luggage Screening in Lobby
Multi Cuisine Commercial Kitchen in Club House 100%
Multipurpose Intelligent games court in Club House 100%
Multipurpose Studio for Yoga Aerobics and Zumba in Club House 100%
Open Parking
Pavilions with shaded seating with Alfresco Dining in Layout 100%
Pedestrian Walking Jogging track in Layout 60%
Restaurant Cafe and banquet hall
Salon and Spa in Club House 100%
Senior Citizens corner in Layout
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Squash Court in Club House 100%
Storm Water Drains
Street Lighting
Study Reading area in Building
Swimming Pool and Deck in Layout 100%
Tennis Court in Layout
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.