SWANAND BLDG NO 33
by HIRANIMANTHAN BUILDERS AND DEVELOPERS
Partnership
Project Information
RERA Certificate No.
P51800004914
Registration No.
REA51800010886
Registration Date
2022-06-22
Developer
HIRANIMANTHAN BUILDERS AND DEVELOPERS Partnership
Architect
Kishore Lotlikar
Project Bank
INDIAN OVERSEAS BANK
Proposed Possession
2019-12-31
Revised Possession
2019-12-31
Extended Possession
2024-11-30
Units Sold
0
Buildings
1
Project Area
1308.93 sq.m
Total FSI
8697.97
Approved FSI
8397.97
SWANAND BLDG NO 33
MahaRERA — P51800004914
MahaRERA — P51800004914
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors21
✅Sanctioned21
🅿️Closed Parking28
📅Completion2019-12-31
Apartment Configurations
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1Bhk | 44.029998779296875 | 0 | 0 | 0 | 0% |
| 1Bhk | 44.66999816894531 | 0 | 0 | 0 | 0% |
| 1Bhk | 45.290000915527344 | 0 | 0 | 0 | 0% |
| 1Bhk | 45.790000915527344 | 0 | 0 | 0 | 0% |
| 1Rk | 31.020000457763672 | 0 | 0 | 0 | 0% |
| 2Bhk | 52.33000183105469 | 0 | 0 | 0 | 0% |
| 2Bhk | 60.130001068115234 | 0 | 0 | 0 | 0% |
Swanand Chs, Bldg No 33
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 44.03 | 1 | 1 | 0 | 100% |
| 1 BHK | 44.67 | 32 | 29 | 3 | 91% |
| 1 BHK | 45.29 | 16 | 15 | 1 | 94% |
| 1 BHK | 45.79 | 7 | 3 | 4 | 43% |
| 1RK | 31.02 | 1 | 0 | 1 | 0% |
| 2 BHK | 52.33 | 1 | 0 | 1 | 0% |
| 2 BHK | 60.13 | 31 | 28 | 3 | 90% |
Construction Progress
SWANAND CHS, BLDG NO 33
Swanand Chs, Bldg No 33
SWANAND CHS, BLDG NO 33
Swanand Chs, Bldg No 33
SWANAND CHS, BLDG NO 33
Swanand Chs, Bldg No 33
SWANAND CHS, BLDG NO 33
Swanand Chs, Bldg No 33
SWANAND CHS, BLDG NO 33
Swanand Chs, Bldg No 33
SWANAND CHS, BLDG NO 33
Swanand Chs, Bldg No 33
RERA Registered Amenities
⬜
Aggregate area of recreational Open Space
⬜
Community Buildings
✅
Electrical Meter Room, Sub-Station, Receiving Station
90%
⬜
Energy management
✅
Fire Protection And Fire Safety
Requirements
90%
✅
Landscaping & Tree Planting
90%
✅
Open Parking
90%
✅
Sewerage (Chamber, Lines, Septic Tank , STP)
95%
✅
Solid Waste Management And Disposal
90%
✅
Storm Water Drains
95%
✅
Street Lighting
90%
⬜
Treatment And Disposal Of Sewage And Sullage Water
✅
Water Conservation, Rain water Harvesting
90%
✅
Water Supply
95%