Project Information

RERA Certificate No.
P51800004498
Registration No.
REA51800010379
Registration Date
2017-08-09
Developer
Gitanjali Infratech Limited Company
Architect
Tarun Motta
Project Bank
AXIS BANK
Proposed Possession
2018-12-31
Revised Possession
2018-12-31
Extended Possession
2019-12-31
Units Sold
0
Buildings
2
Project Area
7937.80 sq.m
Total FSI
18830.47
Approved FSI
18830.47
MahaRERA QR
Tatva
MahaRERA — P51800004498
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors26
Sanctioned26
⬇️Basements1
🅿️Closed Parking1
📅Completion1900-01-01
🏗️Proposed Floors25
Sanctioned25
⬇️Basements1
🅿️Closed Parking1
📅Completion1900-01-01

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
3Bhk 91.66999816894531 0 0 0
0%
3Bhk 91.69000244140625 0 0 0
0%
4Bhk 112.80999755859375 0 0 0
0%
4Bhk 112.87999725341797 0 0 0
0%
4Bhk 113.80999755859375 0 0 0
0%
4Bhk 139.35000610351562 0 0 0
0%

Prayyan

Type Carpet (sq.ft) Total Booked Available Status
3 BHK 91.69 37 30 7
81%
4 BHK 112.88 20 6 14
30%
4 BHK 113.81 20 13 7
65%
4 BHK 139.35 1 0 1
0%

Urja

Type Carpet (sq.ft) Total Booked Available Status
3 BHK 91.67 37 28 9
76%
4 BHK 112.81 20 6 14
30%
4 BHK 113.81 20 11 9
55%

Construction Progress

Prayyan

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises40%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
Stilt Floor 100%

Urja

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises60%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

RERA Registered Amenities

Aggregate area of recreational Open Space 50%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 20%
Energy management
Fire Protection And Fire Safety Requirements 80%
Landscaping & Tree Planting 70%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 80%
Solid Waste Management And Disposal
Storm Water Drains 100%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.