THE ADDRESS BUILDING NO.7/8/9

by STRAWBERRY CONSTRUCTIONS PVT. LTD. Company
Certificate Signed P51700010224
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700010224
Registration No.
REA51700012102
Registration Date
2020-06-16
Developer
STRAWBERRY CONSTRUCTIONS PVT. LTD. Company
Architect
Avinash Mhatre And Associates
Project Bank
PUNJAB NATIONAL BANK
Proposed Possession
2021-06-30
Revised Possession
2021-06-30
Extended Possession
2022-06-30
Units Sold
0
Buildings
3
Project Area
2428.85 sq.m
Total FSI
12866.71
Approved FSI
12866.71
MahaRERA QR
THE ADDRESS BUILDING NO.7/8/9
MahaRERA — P51700010224
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors16
Sanctioned16
🅿️Closed Parking1
📅Completion2020-12-31
🏗️Proposed Floors16
Sanctioned16
🅿️Closed Parking1
📅Completion2020-12-31
🏗️Proposed Floors16
Sanctioned16
🅿️Closed Parking1
📅Completion2020-12-31

Apartment Configurations

Building No 7/8/9

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 36.73 56 49 7
88%
1 BHK 37.26 13 13 0
100%
1 BHK 37.62 52 45 7
87%
1 BHK 38.5 50 48 2
96%
2 BHK 48.75 28 26 2
93%
2 BHK 50.74 2 2 0
100%
2 BHK 52.0 52 52 0
100%
Office space 28.38 1 1 0
100%
Office space 31.89 2 2 0
100%
Office space 33.23 1 1 0
100%
Office space 36.49 1 1 0
100%
Office space 40.49 2 2 0
100%
Office space 40.5 2 2 0
100%
Office space 42.69 1 1 0
100%
Office space 43.72 1 1 0
100%
Office space 44.09 1 1 0
100%
Office space 49.5 1 1 0
100%
Office space 50.3 2 2 0
100%
Office space 51.48 1 1 0
100%
Office space 57.68 2 2 0
100%
Shop 28.38 1 1 0
100%
Shop 31.89 2 2 0
100%
Shop 33.23 1 1 0
100%
Shop 36.49 1 1 0
100%
Shop 40.49 2 2 0
100%
Shop 40.5 2 2 0
100%
Shop 42.69 1 1 0
100%
Shop 44.09 2 2 0
100%
Shop 49.5 1 1 0
100%
Shop 50.3 2 2 0
100%
Shop 51.48 1 1 0
100%
Shop 57.68 2 2 0
100%

Building No 8

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 0 0 0
0%

Building No 9

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 50.76 0 0 0
0%

Construction Progress

BUILDING NO 7/8/9

Basement (if any)100%

Building No 7/8/9

Excavation100%

BUILDING NO 7/8/9

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building No 7/8/9

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

BUILDING NO 7/8/9

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No 7/8/9

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

BUILDING NO 7/8/9

Plinth100%
Podiums (if any) 0%

Building No 7/8/9

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

BUILDING NO 7/8/9

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building No 7/8/9

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING NO 7/8/9

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No 7/8/9

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING NO 8

Basement (if any)100%

Building No 8

Excavation100%

BUILDING NO 8

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building No 8

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

BUILDING NO 8

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No 8

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

BUILDING NO 8

Plinth100%
Podiums (if any) 0%

Building No 8

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

BUILDING NO 8

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building No 8

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING NO 8

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No 8

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING NO 9

Basement (if any)100%

Building No 9

Excavation100%

BUILDING NO 9

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Building No 9

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

BUILDING NO 9

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No 9

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

BUILDING NO 9

Plinth100%
Podiums (if any) 0%

Building No 9

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

BUILDING NO 9

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Building No 9

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING NO 9

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No 9

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management 100%
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 100%
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 100%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.