📞 +91 98200 30685✉️
RERA: A51800043517

Veena Velocity Ph-Ii

by Nikunj Developers
Kept in AbeyanceP99000014147

Project Information

RERA Certificate No.
P99000014147
Registration No.
REA99000025643
Developer
Nikunj Developers
Architect
Kaushik Patel
Project Bank
RBL Bank
Proposed Possession
2017-12-31
Revised Possession
2019-03-31
Extended Possession
2020-09-30
Buildings
5
Project Area
3425.00 sq.m
Total FSI
7991.08
MahaRERA QR
Veena Velocity Ph-Ii
MahaRERA — P99000014147
Scan to verify on MahaRERA portal

Wing-wise Details

🚗Open Parking12
🅿️Closed Parking7
📅Completion2019-03-31
🚗Open Parking12
🅿️Closed Parking7
📅Completion2019-03-31
🚗Open Parking12
🅿️Closed Parking7
📅Completion2019-03-31
🚗Open Parking12
🅿️Closed Parking14
📅Completion2019-03-31
🚗Open Parking11
🅿️Closed Parking11
📅Completion2019-03-31

Apartment Configurations

Wing - A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK54.9426197
73%
2 BHK55.93220
100%
SHOP10.93202
0%
SHOP12.23202
0%
SHOP12.89404
0%

Wing - B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK54.9426179
65%
2 BHK55.93220
100%
Shop10.93202
0%
Shop12.23202
0%
Shop12.89404
0%

Wing - C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK54.9426206
77%
2 BHK55.93202
0%
SHOP10.93202
0%
SHOP12.23202
0%
SHOP12.89404
0%

Wing - D

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK32.74770
100%
1 BHK33.34770
100%
1 BHK36.920200
100%
1 BHK37.19770
100%
1 BHK37.71110
100%
Shop10.93101
0%
Shop11.58101
0%
Shop12.89101
0%

Wing - E

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK32.98770
100%
1 BHK35.15770
100%
1 BHK36.15770
100%
1 BHK36.3770
100%

Construction Progress

Wing - A

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate80%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing88%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Wing - B

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate80%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing88%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Wing - C

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate80%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing88%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Wing - D

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate80%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing88%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Wing - E

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate80%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing88%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station50%
Energy management
Fire Protection And Fire Safety Requirements100%
Landscaping & Tree Planting50%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Solid Waste Management And Disposal50%
Storm Water Drains50%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water50%
Water Conservation, Rain water Harvesting
Water Supply50%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.